Greenwood Ave N

Updated: January 2, 2020

What’s happening now?

Construction is underway on the west side of Greenwood Ave N. Since work began in September, we have installed utility lines that will be able to accommodate the storm water runoff that will come with the new curb and gutter. 

Now, we are beginning to install sidewalks, starting with the curb and gutter between N 140th and 143rd streets. As part of this work, we will pour concrete near driveways of residences and businesses. During this work and while the concrete sets, driveway access may be temporarily unavailable.  If you are impacted you will receive advance notification.

As we get ready to build new sidewalks in early 2020 on Greenwood Ave N, our crews will need plenty of space to work safely. We plan to keep the current roadway configuration, with one lane in each direction, in place until the project is complete in spring 2020. Until then, we ask that drivers be cautious when traveling through the work zone - we appreciate your patience during construction as we work to make these safety improvements!

Questions about the project?

Email the project team at pedestrianimprovements1@seattle.gov or call 206-257-2215.

Project Overview

We are working to repave Greenwood Ave N between N 137th and N 145th streets, as well as adding sidewalks, curbs, and parking strips where they don't presently exist. Other improvements will include Americans with Disabilities Act-compliant curb ramps at each intersection in the project area, pedestrian signal improvements at N 145th St, and a new traffic signal at N 137th St. These improvements will help achieve Seattle's Vision Zero goal to end all traffic deaths and serious injuries by 2030.

The first phase of the project was completed in 2018 and installed a new sidewalk, planting strip, curb, and gutter on the east side of Greenwood Ave N. Crews also installed a new pedestrian-activated traffic signal at N 137th St. 

The second phase of the project, currently underway, will construct a new sidewalk, planting strip, curb and gutter on the west side of Greenwood Ave N between N 136th and N 145th streets. After the sidewalk work is complete, crews will return in spring 2020 to pave the entire roadway on Greenwood.

Project map

Schedule

2016 - 2018: Design phase

June 2018 - December 2018: Phase 1 construction - east side improvements

September 2019 - Early 2020: Phase 2 construction - west side improvements

Spring 2020: Phase 2 construction - repave Greenwood Ave N

Materials

Construction notice (Fall 2019)

Fact sheet (Summer 2019)

Construction flyer (July 2019)

Funding

This project is funded by SDOT's Safe Routes to School Program, Sidewalk Development Program and the Move Seattle Levy, which was approved by voters in 2015.

Get Involved

To sign up for email updates on the project, please contact us at pedestrianimprovements1@seattle.gov or 206-257-2215.

State Environmental Policy Act (SEPA) Review

The Seattle Department of Transportation (SDOT) has determined that the Greenwood Avenue N Pedestrian Improvements Project will not have a probable significant adverse impact on the environment. As a result, SDOT issued a Determination of Non-significance (DNS) on June 25, 2018. This decision was made after review of a completed environmental checklist.