11th Ave NE & 12th Ave NE Paving & Safety Project

Updated: June 23, 2023

What's Happening Now?

We’re hosting in-person drop-in sessions to share information about the project design and answer your questions. Thank you to everyone who attended our first two drop-in sessions! We will post an FAQ in the coming weeks to share responses to the questions we’ve heard. 
We have one in-person drop-in session left! We will be at Cowen Park near the corner of Brooklyn Ave NE and NE 61st St this Saturday, June 24, from 10-11:30AM.

Overview

The 11th and 12th Ave NE paving project was originally included as part of the RapidRide J Line project. In 2020, as Covid-19 reduced budgets, the RapidRide J Line was amended to stop service at the U District light rail station instead of the Roosevelt station as originally planned. Updates were proposed for a new street design for 11th and 12th Ave NE based on community feedback during outreach for the J Line project.

With the shortening of the RapidRide project, we moved the safety and maintenance elements of that project into a separate paving project. Now part of SDOT's Arterial and Asphalt and Concrete (AAC) Paving Program, we'll pave approximately 1.8 miles of 11th and 12th Ave NE to make it safer and more comfortable to travel on, and to extend the useful life of the street. 

This project includes: 

  • Paving between NE 43rd St and NE 67th St 
  • New, accessible curb ramps 
  • Spot sidewalk repair 
  • Traffic signal adjustments 
  • New street safety design, including a new northbound protected bike lane that complements the existing southbound protected bike lane on Roosevelt Way NE  

Construction for this project is expected to begin in late 2023 and finish in 2024. 

Outreach & Project Design

This project is part of our Vision Zero goal to end traffic deaths and serious injuries by 2030. Traffic collisions are preventable through smarter street design, targeted enforcement, and thoughtful public engagement.

Together, we can make Seattle’s streets safer for everyone. In the last 5 years, this project area has experienced a considerable number of injuries from collisions [from 2018].

  • Vehicle volumes: 4,000 – 5,500 per average weekday
  • Vehicle speed: 21 MPH (85th percentile speed)
  • Collisions: 144
  • Injury crashes: 50
  • Serious injuries: 1
  • Fatalities: 0

In addition to taking community feedback, we analyzed traffic and parking data and reviewed freight, transit, bike, and pedestrian master plan recommendations. All these factors informed our designs; therefore, we are adding various safety features to this project, including protected bike lanes and updated traffic signals.

Safety has informed the parking design too, and we are removing parking from one side of the street, while introducing 24/7 parking to the remaining parking spaces so people don’t need to move their cars daily. This project will also include other measures to improve safety and improve all transit options.

Project Map

Map showing the project area

Click this link to enlarge the image

What to expect during construction

Construction is expected to begin in late 2023 And continue through fall 2024. We will send regular email updates with information on upcoming construction activities. We encourage you to sign up for email updates  to stay informed on project activities. 


Typical construction hours are weekdays from 7 AM - 5 PM, with occasional nighttime and weekend work.  

During construction, people can expect:  

  • Temporary lane and street closures for people driving. Detours will be provided and signed. 
  • Temporary sidewalk and crossing closures for people walking and rolling. Detours will be provided and signed. 
  • Temporary local access only restrictions in some areas
  • Disruptions to on-street parking
  • Noise, dust, and vibrations during work hours
  • Construction equipment staged in the work area
  • Pedestrian access will be maintained at all times to businesses and residences  

Schedule

The project is reaching final design. See below for our anticipated project timeline for 11th Ave and 12th Ave NE paving & safety project. Please note that this schedule is subject to change.

  • Late 2023 - Construction begins
  • Fall 2024 - Construction completion

How Can I Get Involved

We're always interested in meeting with community and neighborhood groups that want to learn more about the project and make their voices heard. You can request a briefing by emailing 11th12thPaving@seattle.gov

Funding

This project is part of SDOT's Arterial and Asphalt and Concrete (AAC) Paving Program. Design and construction of our paving projects, as well as the safety and mobility improvements shown, are funded by the Levy to Move Seattle, approved by Seattle voters in November 2015. We also seek additional funding through grants, when available. Learn more about the levy.

Project Materials

To view a PDF of project-related materials, please click on the links provided below:

Transportation

Greg Spotts, Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.