Project Overview

We’re making improvements on the intersection of 35th Ave NE and NE 120th St in Cedar Park to make it safer and more comfortable for people to cross the intersection and access the bus stops. These upgrades were requested by community through the Seattle Transportation Plan outreach process. 

This project is being built as part of the Neighborhood-Initiated Safety Partnership Program, which works with the highest need communities to design and build safety improvements. We expect construction to begin in late 2026.

Project elements include:

  • A new marked crosswalk 
  • A new pair of flashing pedestrian crossing signs 
  • Two new speed cushions on 35th Ave NE
  • Paint and post curb bulbs, which make it easier for everyone to see each other at intersections. To learn more, click here.

Design

Image shows location of design elements on a map.

Schedule

  • 2025: Community engagement and project selection
  • 2026: Design
  • 2026-2027: Construction

Funding 

This project is funded by the voter-approved Seattle Transportation Levy. To learn more, visit seattle.gov/transportation/levy.

Transportation

Angela Brady, Acting Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Sign Up for Latest Updates

Subscribe

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.