Wilson Avenue S Transportation Improvements Project

Updated: July 23, 2019

What’s happening now?

Construction on the Wilson Ave S Transportation Improvements Project is wrapping up. In the coming weeks crews will be working on miscellaneous tasks along the project corridor. Some equipment and materials will remain on the corridor while this work is completed. 

We thank residents and businesses on the project corridor for your patience as crews work to complete this project. 

Check out more details in our latest email update.

Questions about construction? Email the project team at DOT_WilsonAve@seattle.gov or call 206-256-5232

Project Overview

We're working to repave just over 2.5 miles of Wilson Ave S between S Dawson St and S Morgan St. As part of the repaving, we will be taking off the old top layer of the road, placing new asphalt and repainting the lane lines. In addition to repaving, we will also be putting in a new protected bike lane along Wilson Ave S between S Dawson St and S Morgan St. Our goal is to improve the safety, accessibility, and comfort for all users.

Other improvements include:

  • Installing or upgrading curb ramps to be compliant with the Americans with Disabilities Act (ADA)
  • Replacing traffic detection loops that control the signals
  • Repairing and replacing some sections of sidewalk in the project area
  • Bringing storm drainage into code compliance where triggered

Wilson avenue map

Cross section of layout

More information about SDOT's 2018 paving projects

Project Schedule

2016

Initial design and outreach

Spring - Summer 2017

Community outreach continues

Fall 2017

Final design

Late 2017

Advertise for construction

Summer 2018

Construction begins

This schedule if a rough estimation of the project timeline. The schedule is subject to change.

Funding

Total project budget: $2.55 million
Funding Sources:

  • SDOT’s Arterial Asphalt and Concrete Program
  • Sidewalk Safety Repair Program
  • Levy to Move Seattle

Get Involved

If you have any questions, please do not hesitate to contact the project team.

Voicemail: 206-256-5232

Email: DOT_WilsonAve@seattle.gov

More information about other 2018 paving projects

Materials