S Jackson St Corridor Improvements

What's happening now?

Our outreach on this project with stakeholders and neighbors began in spring 2017.

Through this initial outreach, we heard support for pedestrian improvements along the corridor, with requests for additional lighting, bike racks, built-in benches, kiosks, and place-making art. These requests were shared with the project team for consideration. Requests that can’t be funded within this project may be considered for future improvement projects.

You can sign up for email updates or check this website in the summer for more information.

In the meantime, please continue to send us your comments and questions: Email: NSFSJackson@seattle.gov

Project Description

The Seattle Department of Transportation (SDOT) will make improvements along S Jackson St between 20th Pl S and Martin Luther King Jr Way S to enhance pedestrian safety, improve connections and efficiency, and help make this part of S Jackson St the neighborhood's "Main Street." In 2016, the S Jackson St Corridor Improvements project was one of 12 selected by the Levy to Move Seattle Oversight Committee to be funded through SDOT's Neighborhood Street Fund (NSF) program. The NSF program funds projects requested by the community.

Project Elements

Project improvements include the installation of:

  • Extension of the south curb bulb and installation of Rectangular Rapid Flashing Beacons (RRFBs) at the mid-block, marked crosswalk between Dr. Blanche Lavizzo Park and Washington Middle School
  • Real-time information signs (RTIS) at the bus stops at S Jackson St and 23rd Ave S
  • Additional pedestrian lighting along S Jackson St between 23rd Ave S and 26th Ave S
  • Painted curb bulbs with white plastic posts at the intersection S Jackson St and 26th Ave S

Project Benefits

  • Improved visibility and safety for people walking and biking across S Jackson St at Washington Middle School
  • Shorter crossing distance and improved safety for people walking at 26th Ave S
  • Information about bus arrival times for transit travelers

Project Schedule

2016

NSF applications and project selection

2017

Project design

2018

Project construction

2019

NSF applications and project selection (new cycle)

Project Library

Fact Sheet September 2017
Fact Sheet March 2017

SDOT Project Review Document

Project Funding

Funding comes from the 2015 voter-approved, 9-year Levy to Move Seattle, which will improve safety for all travelers, maintain streets and bridges, and invest in reliable, affordable travel options for a growing city. The levy includes $24 million to continue the Neighborhood Street Fund program over the nine years.

Public Outreach and Engagement

We're committed to keeping you informed throughout the life of the project. You can expect outreach to adjacent project neighbors in 2017. Please contact us at any time. Sign up for email updates

Project Contact

NSF Outreach Lead: Cayla Ravanchol
Project phone: (206) 733-9361
Email: NSFSJackson@seattle.gov

To request information in another format:

We're designing and building a transportation project proposed by your neighbors to make it safer for people walking and biking and to strengthen community. To learn more about the project or request translations, call (206) 257-2857.

Estamos disenando y construyendo un proyecto de transporte propuesto por nuestros vecinos a fin de que sea mas seguro para que las personas caminen y monten bicicleta y asimismo fortalecer a la comunidad. Para obtener mayor informacion acerca del proyecto o para solicitar transporte llamar a (206) 257-2857.

Chúng tôi đang thiết kế và xây dựng một dự án giao thông đề xuất bởi chính những người hàng xóm của quý vị nhằm làm cho việc đi bộ và đi xe đạp trở nên an toàn hơn và cộng đồng vững mạnh hơn. Để tìm hiểu thêm về dự án hoặc yêu cầu các bản dịch, hãy gọi (206) 257-2857.

我們正在設計並建造一個由您的鄰居提議的交通計畫,這個計畫旨在改善人們的步行及騎車安全,並強化社區。 如需進一步瞭解這項計畫,或是申請翻譯服務,請撥打 (206) 257-2857.

我们正在设计并建造一个由您的邻居提议的交通计划,这个计划旨在改善人们的步行及骑车安全,并强化社区。如需进一步了解这项计划,或是申请翻译服务,请拨打  (206) 257-2857.

በእግራቸው ለሚጓዙ እና ብስክሌት ለሚጋልቡ ሰዎች ይበልጥ ለደኅንነታቸው አስተማማኝ እንዲሆን በእርስዎ ጎረቤቶች በቀረበ ንድፈ ሐሳብ ላይ በመመርኮዝ የትራንስፖርት አገልግሎት ፕሮጄክትን በመንደፍ እና በማዘጋጀት ላይ ነን። ስለ ፕሮጄክቱ የበለጠ ለማወቅ ወይም ትርጉም አገልግሎት ለማግኘት ጥያቄ ለማቅረብ ወደዚህ ይደውሉ  (206) 257-2857.

በእግሮም ንዝጓዓዙን ብሽክልታ ንዝጥቀሙን ሰባት ውሑስንኦም ንምሕላውን እቲ ማሕበረሰብ ንምጥንኻርን ብጎረባብትኻ ዝተተለመ ናይ መጓዓዝያ ፕሮጀክት ዲዛይን ነውጽን ንሃንጽን ኣሎና፡፡ ብዛዕባ እቲ ፕሮጀክት ዝበለጸ ሓበሬታ ንምርካብ ወይ ናይ ናብ መጓዝያ ንምድዋል ሓገዝ ንምርካብ  (206) 257-2857.

Nuti Pirojektii geejjibaa ollaawwan keessaniin gaafataman kan wixineessinuu fi ijaarruuf, namoota deemaniifi isaan bishikilitii ofaniif daandii nagaa taasisuufi hawaasichas cimsuudhaaf. Waa’ee pirojektichaa caalaa baruuf ykn geejjiba gaafachuuf nuuf bilbilaa  (206) 257-2857.

Waxaynu nakhshadaynaynaa oona dhisaynaa mashruuc gaadiid ay soo jeediyeen dadka deriskaaga ah si aynu ugaga dhigno mid ammaan ah dadka soconaya iyo kuwa baaskiilada wata iyo si aynu u xoojino jaaliyada. Si aad u oggaatid inbaddan oo ku saabsan mashruuca ama u codsatid waxyaabo turjuban soo wac  (206) 257-2857.