Perkins Lane W Retaining Wall Mitigation Project

Updated: September 5, 2024

What's Happening Now!

We are continuing our work on the Perkins Lane retaining wall to address surface slides.

At this time, we are completing the watermain installation and will be pressure testing and inspecting that work over the next few weeks. Following this, Seattle Public Utilities will begin providing connections to the new watermain. We expect that approximately 40 homes will be affected by short-term water shutoffs during the connection process. SPU will notify homeowners in advance of the water shutoffs. Additionally, we anticipate beginning installing the piles for the retaining wall by the end of the month. 

To ensure safety and efficiency during construction, a section of the 2800 block of Perkins Lane W will be closed. We will collaborate with neighbors to provide necessary vehicle access, while maintaining pedestrian access throughout the project, with occasional closures when required. 

What to expect during construction: 

  • Typical weekday work hours of 7am – 5pm, Monday through Friday. 
  • Road closures and detours for people driving, walking, and biking.
  • Short-term water shut downs
  • Some short-term driveway access disruptions
  • Noise, dust, and vibrations during work hours 

Overview

In coordination with Seattle CIty Light and Seattle Public Utilities, we're mitigating against landslides by constructing an approximately 180 feet long, soldier pile wall along the bottom of the slope on the east side of Perkins Ln W. 

THe soldier pile design has been selected to avoid the need for excavation into the slope and follows recent designs implemented during the landslide mitigation work along Rainier Ave S

Project Area

 Map showing position of wall at 2800 Perkins Lane W

Background

SDOT maintains almost 600 retaining walls, most protecting public streets. The average height is 6 feet, and if all the retaining walls and seawalls were lined up end to end, they would extend for 21 miles.

Timeline

Timeline showing we are in the pre-construction phase of the project

Design (Completion winter 2023/24): We’ll collaborate with stakeholders and community members to develop a more detailed final design.   
Construction (as soon as summer 2024): We will construct the project and keep the community informed on the latest construction updates, schedule, and expected impacts.   

Anticipated Construction Impacts

General construction impacts will include noise, dust, vibration, lane restrictions, and potential detours for people walking, biking, and driving.

Funding

The project is funded through the City's Landslide Hazard Mitigation Program and managed by SDOT's Street Use division.

Materials

June 2024: Public Presentation

June 2024: Final Plans

May 2024: Construction Notice

Transportation

Greg Spotts, Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.