RapidRide J Line

The RapidRide J Line project will upgrade streets, sidewalks, pedestrian ramps, streetlights, and traffic signals. It will also add protected bike lanes, replace the water main and sewer on Eastlake Ave E, and create dedicated bus lanes with priority signals and faster boarding.

These improvements will support safer, more connected neighborhoods, improve travel between communities, support local businesses, and expand access to housing. You can download final project maps using this link.

Updated: July 10, 2026

What's happening now

We have resumed construction on the RapidRide J Line Project.

During the FIFA World Cup, crews paused work and temporarily created some parking areas on the west side of Eastlake Ave E. These parking areas have now been permanently removed, so we can complete our work. 

We have also put back the northbound detour onto E Allison St and Harvard Ave E. This allows us to store materials in the northbound lanes of Eastlake Ave E between E Allison St and Harvard Ave E.  

Image shows construction equipment on Eastlake Ave E between E Louisa St and E Roanoke StImage above shows construction equipment on Eastlake Ave E near E Louisa St.

University District Construction  

Electrical and sidewalk work in the University District  

Crews are performing electrical work in many areas in the University District. 

This week, we resumed work on the northbound RapidRide J Line bus stop at the intersection of NE 41st St and Eastlake Ave NE, near 11th Ave NE. Crews are installing foundations for poles and other electrical wires needed at the new bus stops. They are also creating the stairs and sidewalks around the bus stop. We will shift traffic to the west side of the street, and one lane will remain open. Please follow the signs and directions from crews if you are using the sidewalk.  

You may also see crews working on Roosevelt Way NE between NE 42nd St and Campus Parkway. Traffic will be moved over to make room for us to work. One lane will remain open.

Image shows a pedestrian detour from the sidewalk on Roosevelt at NE 42nd St. Detour moves people into a protected walkwayThe map above shows a protected walkway at NE 42nd St to help people move around our workzone. It also shows temporary parking on NE 42nd St to assist visitors to the UW Clinic.

A mixed-use path will be provided for pedestrians and people on bikes near the work area at Roosevelt Way NE and NE 42nd St.  

As early as Thursday, July 16, crews will continue electrical work on the west side of Roosevelt Way NE near the UW Clinic. During this work, the entrance to the UW Clinic is accessible. However, as seen in the map above, we will need to close part of the sidewalk where we are working. A multi-use path is installed around the work area on Roosevelt Way NE, directing pedestrians to the UW Clinic. People riding bikes will be asked to dismount and walk through the construction area using the mixed-use path. 

The UW Clinic shuttle pick-up and drop-off area will be located on the north side of NE 42nd St. The non-shuttle pick-up and drop-off area will be located on the south side of the street.  

During this work, we will need to close the bus stop near NE 42nd Street. For information on bus stop relocations during construction, we encourage you to visit King County Metro’s website. The north crosswalk at NE 42nd St and Roosevelt Way NE will also be closed. The east and south crosswalks remain open. 

Eastlake Construction  

Map shows the various work zones along Eastlake Ave E The map above shows the various places where we will be working within the Eastlake neighborhood in the coming weeks. 

Street closures in Eastlake 

As shown on the map above, we have closed several areas in Eastlake for construction activities and equipment storage. The areas experiencing closures include:    

  • The northwest sidewalk corner of Eastlake Ave E and E Allison St.
  • The northwest street corner at Eastlake Ave E and E Hamlin St.
  • The west side of the Eastlake Ave E and E Edgar St intersection.
  • The west side of Eastlake Ave E between E Roanoke St and E Lynn St.
  • The northwest sidewalk corner of Eastlake Ave E and E Garfield St. 

Image shows the construction team working at the intersection of Eastlake AVe E and E Edgar StThe image above shows our team working at the intersection of Eastlake Ave E and E Edgar St.

Electrical and sidewalk work along Eastlake Ave E    

Over the next few weeks, you’ll see crews installing foundations for poles that will support traffic signals and the electrical wires powering the RapidRide J Line. This work is taking place on Eastlake Ave E between E Shelby St and E Edgar St. 

As paving progresses on Eastlake Ave E, crews are shifting their focus to installing new electrical wiring, replacing sidewalks, and building new accessible pedestrian ramps to make getting around much safer and easier. Crews will perform this work at several corners, including: 

  • The northwest corner of Eastlake Ave E and E Allison St started this week.
  • The northwest corner of Eastlake Ave E and E Garfield St started this week.
  • The southeast corner of Eastlake Ave E and E Blaine St
    •  Only sidewalk demolition and paving work will take place. 
  • The northeast corner of Eastlake Ave E and E Fuhrman St, starting on July 13.
    • A multi-use path will guide pedestrians and people on bikes around the work area. 
  • The northwest corner of Eastlake Ave E and E Hamlin St
  • The northwest corner of Eastlake Ave E and E Shelby St 
    • Only sidewalk demolition and paving work will take place.
  •  The southwest corner of Eastlake Ave E and E Shelby St

Work at each corner is expected to take several weeks to complete. During this time, we will need to temporarily close sections of the sidewalk and direct pedestrians and people on bikes around the work areas or to the opposite side of the street. Additionally, we may need to close the right lane on Eastlake Ave E near the work area to provide accessible pedestrian routes. Please follow all signs and instructions from crews. 

The image shows the street surface along Eastlake Ave E being made ready for demolitionThe image above shows the street surface with holes punched into it near E Louisa St. These holes make it easier to break the old street surface during demolition. 

Upcoming weekend paving at Eastlake Ave E and E Hamlin St 

Starting this Friday, July 10, crews began work on the northwest section of the street at Eastlake Ave E and E Hamlin St. Crews will demolish the area on Friday, pour new concrete on Saturday and Sunday, and reopen it on Monday morning. During this time, we will shift traffic to the east side of the street, and one lane will remain open in each direction. Flaggers will help guide vehicles on E Hamlin St around the work area.  
 
The following weekend, crews will repeat this process on the southwest corner of the street. We are working on weekends to reduce the impact on weekday traffic. Thank you for your patience and understanding.

Street paving along Eastlake Ave E 

We are working on the final areas of street constrcution along Eastlake Ave E. Crews have resumed their work of building a new, smooth, and long-lasting concrete street. We are actively demolishing, preparing, and pouring new concrete in several areas: 

  • The west side of the Eastlake Ave E and E Edgar St intersection: Crews expect to finish this work next week.
  • The west side of Eastlake Ave E between E Roanoke St and E Lynn St: Demolition is expected to continue for the next week, followed by preparing the new road and then pouring concrete.
  • The northwest section of Eastlake Ave E and E Roanoke St, starting as soon as July 15.
  • The west side of Eastlake Ave E and E Galer St, starting as soon as July 17.
  • The northwest section of Eastlake Ave E and E Lynn St, starting as soon as the weekend of July 24. 

Fairview Ave N Construction 

One southbound lane of Fairview Ave N remains closed as we widen the west side of Fairview Ave N between Eastlake Ave E and Valley St. Crews will continue to demolish the area and pour new concrete. 

Crews will also begin working on the west side of Fairview Ave N and Yale Ave N, where they will install foundations for poles that will support traffic signals and the overhead electrical wires powering the RapidRide J Line.  As early as July 16, crews will install underground electrical wires and new sidewalks at the northwest corner of the intersection. Similar work will then take place at the southwest corner later in the month.   

South Lake Union Construction 

This week, crews began removing the sidewalk at the southwest corner of Fairview Ave N and Valley St. Over the next week, they will install underground electrical wires and pour concrete for the new sidewalk. 

This month, crews will be demolishing the sidewalk, installing electrical wires, and pouring new concrete in several areas in South Lake Union. This includes: 

  • The southwest corner of Fairview Ave N and Valley St
  • The northwest corner of Fairview Ave N and Yale St
  • The southwest corner of Fairview Ave N and Yale St

At Fairview Ave N and Harrison St, crews will install cabinets to hold electrical utilities for the southbound and northbound RapidRide J Line bus stops. This work will begin as early as July 14. You’ll also see crews building a traffic signal at Valley St starting as early as July 15. 

It was Great Meeting so Many of You Last Week!

Image shows community members meeting staff members near Eastlake Coffee as we handed out free Lime helmetsImage shows community members meeting with RapidRide J Line staff outside of Eastlake Coffee. 

Last week, the RapidRide J Line team gave away more than100 free Lime safety helmets for people who ride bikes and scooters. Thank you to all who stopped by to pick up a helmet, ask questions, and learn more about the project. We truly appreciate your questions, kindness, and support!

Monthly Online Open House Update

Thank you to all the residents and business owners who have joined our online open house this past year! We have addressed concerns, gathered feedback, and shared project information. 

As the project progresses, we are getting less questions and therefore decided to switch our online open houses to the first Thursday of each month. Our next open house will be on Thursday, July 2, from 2 to 3 PM. We encourage everyone to join us and be part of the conversation.  

If you haven't used Microsoft Teams to engage with the project team, please view this tutorial. There is information available about how to use your camera, mute and unmute yourself, and chat with other meeting participants. We are also available to offer technical support during our drop-in session if you encounter any issues as well. We look forward to connecting with you! 

You can access the online meetings with the details below:
Meeting link 
Meeting ID: 237 305 138 093 
Passcode: mBSfNf

You can download a PDF that shows the upgrades this project will make by clicking this link.

We plan to upgrade from the existing Route 70 to the RapidRide service in 2027.

Sign Up to Learn More

If you would like to learn more about project updates and schedule you can subscribe to receive our project emails.

King County Metro's University Bridge Trolley Pole Replacement Project 

This summer, King County Metro will begin replacing the poles and their foundations on the University Bridge. These structures are reaching the end of their life cycle and must be replaced to improve lighting and support reliable, ongoing trolley service. The bridge will remain open during the project, with some lane reductions, sidewalk closures, and pedestrian detours. To learn more about this King County Metro project, visit the project website. 

Project Overview

We're partnering with King County Metro (KCM) to enhance transit connections and upgrade existing bus routes to Metro RapidRide service. The project upgrades the current Route 70 to a RapidRide level of service, improving transit connections to  Downtown, Belltown, South Lake Union, Eastlake, and the University District neighborhoods. In addition to improving bus reliability with all day transit service, the project will install new bus stations, repave streets, add new protected bike lanes, and improve pedestrian accessibility.

The RapidRide J Line project also addresses current and future mobility needs for travelers, transit capacity constraints along the route, and provides equitable transportation access to major institutions, employers, and neighborhoods.

Water main replacement wraps up on Eastlake Ave E! 

We have completed the installation of new water mains for the RapidRide J Line project! This marks the last major effort to upgrade the water system in the area, ensuring reliable, earthquake-resilient water infrastructure for years to come.

By the numbers, we’ve installed: 

  • More than 9,000 feet of upgraded water main (the length of 25 football fields)
  • 27 new fire hydrants
  • 174 new connections to homes and businesses

By replacing aging pipes, this effort ensures a dependable supply of clean drinking water, reliable water access for the Seattle Fire Department, and new pipes that meet modern standards, reducing the need for construction and maintenance in the future.

We worked in close partnership with Seattle Public Utilities, which helped fund the utility work and support installation alongside the project contractor. <>/p

For more information on the water main installation and what’s next, check out our blog post.

The RapidRide J Line project will:

  • Improve transit travel time and reliability throughout the route by adding transit lanes and transit signal priority  
  • Provide a high-quality rider experience with stations that include shelters, lighting, real-time arrival information, and all-door boarding
  • Improve access to transit through upgraded curb ramps, sidewalks, and signals
  • Improve connections to Link light rail, other bus lines, and Seattle Streetcar
  • Install protected bike lanes to improve safety of all travelers
  • Reduce greenhouse gas emissions with more transit options and fewer cars on the road
  • Pave Eastlake Ave E from E from Fuhrman Ave E to Fairview Ave E with at least 12 inches of concrete, creating a roadway that will last more than 50 years
  • Partner with Seattle Public Utilities to replace the existing watermain on Eastlake Ave E 

The RapidRide J Line project will bring many improvements to the neighborhoods served by the upgraded bus route. These improvements include: 

  • 15,130 feet of repaired sidewalks
  • 2 miles of repaved roadway
  • 3.7 lane-miles of protected bike facilities
  • 2 miles of bus priority lanes
  • 177 improved crosswalks
  • 33 intersections with traffic signal improvements, including 253 new traffic signal devices
  • 190 newly planted trees
  • 8,900 feet of  watermain replacement, in partnership with Seattle Public Utilities 

The links below connect to videos highlighting some of the changes that will be in place once the work is complete:  

Station Amenities

The following amenities will be included at RapidRide J Line stations:

  • A 12-ft bus shelter canopy
  • Real-time arrival information
  • All-door boarding
  • Benches
  • Pedestrian-level lighting
  • Signature signposts and route information maps

Graphic showing components of a typical RapidRide bus station.

Project Map

You can see the changes this project will make along the entire route by downloading the final design plans.  

Map showing length of project from downtown up to the U DIstrict

 Click this link to download a higher resolution map

A chart showing different project phases including planning, design and construction.  An arrow says 'we are here' on 'during construction'

  • Planning (2014-2017): We collected traffic data, reviewed plans, and gathered community experiences to define options.
  • Design (2017-2023): We are collaborating with the community, working to secure regulatory approval (e.g., Environmental Assessment), and developing a more detailed final design.
  • Construction (2024): We are constructing the project and will keep the community informed on the latest construction updates, schedule, and expected impacts.
  • Service launch (planned for 2027)

Funding

RapidRide J Line is partially funded by the 9-year Levy to Move Seattle, approved by voters in 2015. Additional funding is being sought through a Federal Transit Administration Small Starts Grant.

Contact Information

We're always interested in meeting with community and neighborhood groups that want to learn more about the project.You can request a briefing by emailing RapidRide@seattle.gov or calling (206) 257-2202.

Construction Outreach Materials

As construction continues, we will house all construction related outreach materials within this section. 

November 2024

September 2024

Trees are fundamental to the character of Seattle and to our quality of life. In our rapidly changing climate, Seattle's urban forest is an increasingly important asset, playing a critical role in mitigating climate change impacts, including heat island effects, as well as supporting Seattle's public health, providing habitat for wildlife, creating spaces for exploration and enjoyment, cleaning our air and water, and reducing the quantity of stormwater runoff, further helping water quality.  

The RapidRide J Line project will remove 92 trees in areas where we will widen sidewalks and install new bus shelters. As part of the tree mitigation plan, we will plant approximately 190 new trees, which have been chosen based upon their suitability for an urban environment. Once the project is complete, there will be a net gain of 98 trees. 

The map below identifies where trees are being retained and removed, as well as where new trees will be planted. 

Image shows map of where trees will be remove or planted throughout the projectClick this link to download a larger version of the tree map above.

The Rapid Ride J Line project area includes nine existing permanent artworks from the City of Seattle’s Public Art Collection. The Office of Arts & Culture is working closely with Seattle Department of Transportation to protect the artworks during construction. The three artworks that will be impacted include:

  • “Dreamboats” by Linda Beaumont will stay in place and be protected as needed during construction
  • “Lost in Thought” by Ellen Sollod will have one of three ground mosaics removed and reinstalled during construction
  • “Cornerstones” by Stacy Levy will see all thirty-two concrete and glass inlay artworks deinstalled and reinstalled during construction. As part of the deinstallation and reinstallation, ARTS will work with the artist to repair, remake, and restore the damaged and missing artwork prior to reinstallation. 

For more information about the Public Art program, visit the Office of Arts & Culture’s Public Art webpage or email the Office of Arts & Culture at arts.culture@seattle.gov.

RapidRide J Line outreach conducted to date

 From 2015-2023 the project has engaged the public with: 

  • 115 community meetings and briefings
  • More than 1,685 community members engaged
  • Emails and mailers to more than 40,000 neighborhood residents and businesses 

Date Event
Phase 1 - Mode Analysis and Existing Conditions
February 2015                              Presented to Eastlake District Council meeting
Phase 2 - Characteristics of BRT and Multimodal Components
March-April 2015 Key stakeholder group outreach, including phone calls to develop an outreach list
May 2015 Open houses (2) to discuss mode analysis and existing conditions
July 2015 Joined Cascade Bicycle Club for walking audit of Eastlake Ave E
August 2015 Presentation to South Lake Union Chamber of Commerce
September 2015 Forum meeting in South Lake Union to discuss mode options
September 2015 Forum meeting in South Lake Union to discuss mode options
October 2015 Presented to Eastlake District Council meeting
November 2015 Forum meeting in South Lake Union to discuss BRT in-depth
November 2015 Presented to Roosevelt Neighborhood Association
December 2015 Open houses (2) to discuss BRT and multi-modal options
January 2016 Presented to Maple Leaf Community Council
January 2016 Presented to University Transportation Committee
January 2016 Presented to Eastlake Community Council
March 2016 Presented to U-District Partnership
March 2016 Project staff conducted business access survey
Phase 3 - Recommended Corridor Concept
May 2016 Forum meeting to review recommended corridor concept
June 2016 Presentation to Seattle Transit Advisory Board
June 2016 Presented to Fred Hutchinson staff
June 2016 Open houses (2) to review recommended corridor concept
July 2016 Reviewed recommended corridor concept with Vulcan staff
September 2016 Presentation to Seattle Bicycle Advisory Board
July 2017 Submitted Locally Preferred Alternative to Seattle City Council (approved July 2017)
November 2017 Notifications for public scoping meeting: • Email update • Mailed notice
December 2017 Public scoping open house to inform project Environmental Assessment
March 2018 Attended Eastlake Community Council meeting
April 2018 Attended Eastlake Community Council meeting
August 2018 Project email update
September 2018 Presentation to Seattle Bicycle Advisory Board
October 2018 Notifications for Eastlake neighborhood question and answer meeting: • Email update • Mailed notice
October 2018 Hosted Eastlake neighborhood question and answer session to review bicycle alternatives analysis and parking analysis
December 2018 Email invitations sent for Eastlake community parking workshop
January 2019 Hosted Eastlake community parking workshop to discuss opportunities for RPZ updates, transportation options, shared parking, and load zone relocations
April 2019 Attended Eastlake Community Council meeting
April to June 2019 Project outreach staff conducted door-to-door access surveys for Eastlake businesses
May 2019 Attended WSDOT/SDOT community parking briefing to review parking effects from the SR 520 project
July 2019 Briefing with Friends of Seattle's Olmsted Parks to review the Ravenna Boulevard park
July 2019 Briefing with members of Eastlake Community Council and SAFE Eastlake
July 2019 Notifications for Eastlake business parking workshops: • Mailed notice • Emailed notice • Door-to-door flyers
July 2019 Hosted Eastlake business parking workshops to discuss opportunities for load zone relocations, transportation options, shared parking, and RPZ updates
October 2019 Hosted U-District and Roosevelt Open House and Question & Answer Session
October 2019 Hosted Eastlake, South Lake Union and Downtown Open House and Question & Answer Session
October 2019 Captured community feedback through online open house
October 2019 Presentation to Seattle Transit Advisory Board
October 2019 Briefings with:
  • Eastlake Coffee
  • Patrick's Fly Shop
November 2019 Briefings with:
  • Seattle Public Library
  • Eastlake Fitness and DJ's Apartments
  • Seattle Children's Hospital
January 2020

Notifications for Environmental Assessment and Section 4(f) comment period:

  • Mailed notice
  • Emailed notice
  • Notice at Seattle public libraries
  • Notice of availability
January 2020 Hosted U District, Roosevelt, Eastlake, and Downtown Drop-in Sessions for Environmental Assessment and Section 4(f) comment period.
January 2020 Briefing with the Eastlake Community Council Board.
February 2020 Briefing with the University of Washington.
December 2020 Route Update Public Meeting(virtual).
December 2020 (Add new line) Attended North Link Connections Mobility Board meeting
January 2021 Briefing with Councilmember Alex Pedersen
March 2021 Briefings with:
  • U District Partnership
  • Belltown United
March 2021 Attended Roosevelt Neighborhood Association meeting
March 2021 Attended North Link Connections Mobility Board meeting
May 2021 Attended Northeast District Council meeting
June 2021 Briefings with: 
  • Councilmember Girmay Zahilay
  • Council staff
  • SpotHero
  • Interbranch Transit
June 2021 Attended Mercer Corridor Stakeholder Committee meeting
July 2021 SpotHero demo at Eastlake Community Council Board meeting
August 2021 Briefings with:
  • Prime Parking
  • UW Student Life
October 2021 U District Link light rail station grand opening tabling
October 2021 Email update to community-based organizations to take Supplemental EA Survey
October 2021 Presentation to the Seattle Bicycle Advisory Board
November 2021 Received community feedback through Supplemental EA Survey
December 2021 Briefing with:
  • Vulcan
  • Eastlake Community Council Board
  • Property owners on Eastlake Ave
January 2022 Project team responded to email inquiries about shortened route
February 2022 Project communications with:
  • Seattle Neighborhood Greenways
  • Cascade Bicycle Club
February 2022 Project outreach staff conducted door to door notification of geotechnical boring work
March 2022 Briefing with:
  • Eastlake Fitness
  • Property owners on Eastlake Ave
April 2022 Briefing with Eastlake Community Council
May 2022 Project email update about FONSI
May 2022 Briefing with Seattle Police Department
July 2022 Briefing with Vulcan
August 2022 Project outreach staff conducted door to door notification of geotechnical boring work
August 2022 Project email update for geotechnical boring work
August 2022 Presentation to Eastlake Community Council
September 2022 Captured community feedback through Community Design Survey
September 2022 Notifications for virtual Multimodal Engagement Sessions
  • Sent mailer
  • Sent invitation through project email update
September 2022 Hosted virtual Multimodal Engagement Sessions
September 2022 Project email update with follow up from Multimodal Engagement Sessions
September 2022 Briefings with:
  • Seattle Neighborhood Greenways
  • Eastlake Community Council
  • U District Partnership
October 2022 Briefings with:
  • University of Washington Transportation Services
  • Seattle Pedestrian Advisory Board
November 2022 SDOT Director Greg Spotts Walking and Listening Tour along Eastlake Ave
February 2023 Briefings with:
  • Seattle Police Department
  • General Services Administration
March 2023 Briefings with:
  • Fred Hutch
  • Seattle Police Department
March 2023 Briefings with Escala Condominiums
April 2023 Briefings with Eastlake Community Council
May 2023 Briefings with:
  • U District Partnership
  • Spruce Street School
June 2023 Briefings with Vulcan
July 2023 Briefings with:
  • Commute Seattle
  • MKA, Aedas, and Seattle Children’s Hospita
August 2023 Briefings with:
  • Eastlake Community Council
  • G3 and Associates
  • Seattle Police Department
September 2023 Briefings with:
  • Harvard Avenue Parking
  • TOPS K-8 School
October 2023 Briefings with:
  • Pembroke
  • UW Transit
November 2023 Briefings with:
  • Escala Condominiums
  • Mercer Corridor Group
December 2023 Briefings with Pembroke
January 2024 Briefings with South Lake Union Community Council

Project Materials

December 2025

September 2024

March 2024

Updated project maps (January 2024)

Videos highlighting changes along the route (Oct 2023)

Project Maps (June2023)

March 2023

December 2022

September 2022

May 2022

Previous National Environmental Policy Act Materials 

October 2021

Supplemental Environmental Assessment Appendices

Scroll down to view the January 2020 Environmental Assessment

April 2021

February 2021

January 2021

December 2020

January 2020
 Environmental Assessment Appendices

October 2019

July 2019

April 2019

January 2019

October 2018

September 2018

December 2017 - Environmental Scoping

July 2017

June 2017

June 2016 Open Houses

December 2015 Open Houses

May 2015 Open Houses

Reference Documents

Transportation

Angela Brady, Acting Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Sign Up for Latest Updates

Subscribe

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.