Magnolia Bridge Preservation Project
July 2026
What’s happening now?
You may see crews wearing safety vests on or near the Magnolia Bridge this summer and into the fall. Crews will perform various surveying and field investigation activities to collect data that will inform repair and rehabilitation plans for future construction work essential to improving and preserving the bridge. Please slow down when crews are present and mind all traffic laws.
About the Project
The Magnolia Bridge Preservation Project will keep the bridge in reliable working condition by completing structural repairs and rehabilitation to the portions of the Magnolia Bridge west of the railroad tracks.
The repair work is expected to include and not limited to concrete and steel repairs, structural strengthening, bridge deck restoration, and expansion joint repairs. As part of this project, we'll evaluate and consider improvements to the seismic resiliency of the structure, depending on funding.
Aerial view of Terminal 91, the Magnolia Bridge, and the Magnolia neighborhood.
Project Area
Project Schedule
- Fall 2026 - Initial existing structure assessment and field inspection.
- Spring 2027 - Alternatives development and evaluation.
- Summer 2027 - 30% design.
- Spring 2028 - Final design.
Bridge Background
The approximately 2,650-foot-long Magnolia Bridge was built in 1930 and connects the neighborhood of Magnolia to Smith Cove Park, Elliott Bay Marina, Terminal 91, Elliott Bay businesses, and 15th Ave W. The bridge carries 17,000 vehicles per day over across the southern portion of Interbay.
The Seattle Department of Transportation (SDOT) identified a portion of the bridge west of the railroad tracks in need of repairs so it can continue to sustain its current level of operations.
The Magnolia Bridge was originally built in 1930 and connects Magnolia to Smith Cove Park, Elliott Bay Marina, Terminal 91, Elliott Bay businesses, and 15th Ave W.
Nearby projects
We will be coordinating with the following capital projects in the neighborhood:
Funding
Bridge repairs and strengthening improvements are funded by the voter-approved 2024 Seattle Transportation Levy. To learn more, visit seattle.gov/transportation/levy.

We are exploring local, state, and federal sources to fund the sidewalk widening and sidewalk and trail connections on the west side of the bridge.