Andover and Dakota Pedestrian Safety Enhancements
Updated: March 1, 2023
What's happening now?
We're building new curb ramps and intersection improvements at 38th Ave S and S Andover St. Construction is scheduled to begin as soon as early March and last until mid-April.
To ensure a safe and efficient work site to complete the concrete panel replacement and curb bulb work, there will be intersection closures over weekends. The concrete needs to cure for a minimum of 24 hours so the intersection will be closed from Saturday morning until Sunday evening. Weekend work is tentatively scheduled as follows:
- Saturday, March 4 through Sunday, March 5
- Saturday, March 11 through Sunday, March 12
- Saturday, March 18 through Sunday, March 19
- Saturday, March 25 through Sunday, March 26
We have reserved the crews for the first two weekends in April, in case they need additional time to complete the work. Crews will try to do some ADA ramp work during the week, if possible.
Weekend Intersection Closures Detour Map
During the weekend intersection closures, local access will be maintained on 38th Ave S and S Andover St with a detour route on S Charlestown St, 39th Ave S, and S Dakota St. We will have temporary no parking along the detour to maintain access for trucks.
We will provide updates here as well as through the project inbox. If you would like to stay informed on the project's progress, please sign up for email updates.
Project Overview
Elements
- Accessible (ADA) Ramps
- Curb Bulbs
- Concrete Panel Replacement
- Sign and marking updates
Benefits
- Safety improvements to the intersections will facilitate crossings for people walking and biking
- New ADA-compliant curb ramps will improve access
- Curb bulbs have been shown to improve pedestrian crossing safety
- Speed cushions have been shown to calm traffic speeds
Design
Earlier project materials included a marked crosswalk at 38th Ave S and S Andover St. This was an oversight, and the concepts on this page now reflect the proposed design. While a marked crosswalk is not included in the project design, the new curb bulbs and curb ramps will improve access and shorten the crossing distance for people walking and rolling. These improvements will also make people walking and rolling more visible to drivers and encourage slower vehicle speeds on 38th Ave S. Once the curb bulbs are complete, we can monitor this location to see if any additional improvements should be considered.
Project Background
This is one of the 15 Neighborhood Street Fund projects requested by neighbors and selected by the Levy to Move Seattle Oversight Committee. Neighborhood Street Fund is a city program, running on 3-year cycles, that enables neighbors to propose and help prioritize transportation-related projects that are then built by the Seattle Department of Transportation (SDOT).
Note: funds not used for this project will be returned to the NSF program budget.
Schedule
The NSF program runs on 3-year cycles to select, design, and build projects, but we had project delays this round with design updates and schedule impacts due to SDOT's work responding to the COVID-19 pandemic. The application phase for the 2019-2021 cycle opened October 2018 and projects will be constructed in 2022 and 2023.
Phase | Timeline |
---|---|
Applications | 2018 |
Community Prioritization and Voting | 2019 |
Design | 2020 |
Construction | 2022-2023 |
Questions?
If you have questions or need translated materials, please contact us at NSF_AndoverDakota@seattle.gov or 206-727-3581. Thank you.
Servicios de traducción e interpretación disponibles bajo petición 206-727-3581.
Matutulungan ka naming maintindihan kung hihingi kang tulong 206-727-3581.
요청하시면 번역이나 통역을 제공해드립니다 206-727-3581.
Dịch và thông dịch viên sẵn sàng nếu có sự yêu cầu 206-727-3581.
Haddii aad dooneyso turjubeen fadlen wac 206-727-3581.