City Wide Pools

Updated: June 26, 2018

Summer 2018

As a project management efficiency, Seattle Parks and Recreation, Planning and Development Division (PDD) consolidated needed citywide pool repairs into one bid package. Bids opened on April 25 and all bids had to be rejected.  Project has been rebid and bids open June 27 for the City Wide Pools project addressing needed structural improvements to seven existing pools:

  • Meadowbrook - Selective pool deck slab demolition and replacement. Selective pool deck drains demolition and replacement. Selective repair of pool edge apron. Replacement of Natatorium air handing unit and associated duct work at Meadowbrook Pool. 
  • Queen Anne - Selective pool deck slab demolition and replacement. Selective pool deck drains demolition and replacement. Repair damaged structural beams and pool deck. 
  • Medger Evers - Refurbish existing pool bulkhead. Selective pool deck slab demolition and replacement. Selective pool deck drains demolition and replacement.  Install new plaster liner. Repair SBS membrane roof at stair tower/mechanical room roof. 
  • Pop Mounger - Remove and replace existing pool liner. 
  • Southwest - Remove and replace existing pool liner. 
  • Madison - Refurbish existing pool bulkhead. Demolish and replace roof, install insulation and provide seismic structural upgrades.  Demolition and repair of stucco walls, siding, and clerestory windows. Demolish and replace lighting fixtures. 
  • Ballard - Demolish and replace existing concrete pool deck, pool deck drains, pool & spa plaster liner and replace existing pool filter system. 

Construction is planned to commence at the first pool in August and conclude in December 2019.

Planned Closure Dates:

Each pool will be closed one at a time to complete needed renovations.

  • Meadowbrook Pool: To be determined (TBD)
  • Queen Anne Pool: October 8 - December 28, 2018
  • Medgar Evers Pool: January 2 - May 10, 2019
  • Mounger Pool: March 18 - April 12, 2019
  • Southwest Pool: April 29 - May 24, 2019
  • Helene Madison Pool: May 20 - October 4, 2019
  • Ballard Pool: October 21 - December 20, 2019

Location

Schedule

Bidding, Planning & Design: April - July 2018
Construction: August 2018 - December 2019

Project Description

As a project management efficiency, Seattle Parks and Recreation, Planning and Development Division (PDD) consolidated needed citywide pool repairs into one bid package. Bids opened on April 25 for the City Wide Pools project addressing needed structural improvements to seven existing pools.