Fairmount Playground Softball Infield Conversion
Updated: November 6, 2026
Fall 2026
Seattle Parks and Recreation (SPR) has begun planning to convert the Fairmount Park softball infield from clay/silt soil mix to synthetic turf. Our design consultant, D.A. Hogan has created site plans for the project and is will assist through construction. The entire field will be closed during construction. SPR and the contractor hired for the project will work to minimize impact on the roadwas and neighborhood. SPR continues to deliver a safe, durable, and playable athletic facility and experience for users.
Project Improvements
- Convert the existing dirt infield to synthetic turf.
- Upgrade dugouts.
- Improve the backstop system.
- Enhance field usability and reduce weather-related impacts.
Location
Fairmount Playground, 5400 Fauntleroy Way SW, Seattle, WA 98136
Budget
The total budget for this project is $1.5 million, secured through the Real Estate Tax (REET) Capital Fund.
Schedule
Planning: Spring 2025 - Fall 2025
Design & Permitting: Fall 2025 - Summer 2026
Construction: December 2026 - February 2027
Completion: February 2027
Project Description
This project aims to expand playing options for youth softball at Fairmount Playground and support safe, accessible, and quality play for users on a year-round basis, including during inclement weather. This project will convert the softball infield from clay/silt soil mix to synthetic turf, including updates to the dugouts and backstop, as well as pathway accessibility improvements.
The Fairmount Playground Softball Field will be closed during construction. SPR will work with our design team and athletic scheduling team to limit the impact on field users.