Meridian Playground Play Area Improvements
Updated: October 31, 2023
Fall 2023
This project aims to make site improvements to a play area located within the western half of the former Home of Good Shepherd property. Most components of the play area were constructed in the early 1980s, revised in 2002, and some equipment was replaced through a Neighborhood Matching Fund project in 2011. Several elements/features within the play area such as existing play equipment, art paving, play area ramps, custom made slides and rubber tiles need to be renovated or replaced.
Location
Meridian Playground, 4649 Sunnyside Avenue North, 98103
Budget
$1,155,000 in funding is provided by the Real Estate Excise Tax (REET)
Schedule
Public engagement and design process: Fall 2023 - Winter 2023/2024
Design and Permitting: Spring 2024 - Winter 2024/2025
Construction: Spring 2025 - Winter 2025/2026
Project Description
This play area project will replace the play equipment and make accessibility improvements to route from the main parking area and in the comfort station in compliance with the Americans with Disabilities Act (ADA).