International District/Chinatown Community Center Alcove Safety Renovation
Updated: July 22, 2025
Summer 2025
Seattle Parks and Recreation (SPR ) is launching a project to address safety concerns raised by staff and patrons regarding the front and rear entrance alcoves of the International District/Chinatown Community Center building.
We hired a design consultant and completed conceptual designs for the entrance gates. The consultant is currently working to receive approval from permitting and review agencies for the project.
Location
International District/Chinatown Community Center, 719 8th Ave S, Seattle, WA 98104
Budget
The total budget for the project is $300,000, funded by the Seattle Metropolitan Park District.
Schedule
Design, Permitting and Agency Review: Summer 2025 – Fall 2025
Construction: Fall 2025 - Winter 2026
Project Description
SPR is launching a project to address safety concerns raised by staff and patrons regarding the front and rear entrance alcoves of the International District/Chinatown Community Center building.
The project will install secure gates to enclose the front entrance alcove off 8th Ave S and rear alcove in the alley. The front entrance gates will remain open during community center operating hours and have no impact on normal use and access to the community center.