Dahl Playfield Restroom Renovation
Updated: September 30, 2026
Fall 2026
Seattle Parks and Recreation (SPR) identified the Dahl Playfield Restrooms in 2023 as a renovation project. The restroom caught fire during the design development phase and now requires additional work to address the fire incident. The project scope now includes structural repair, roof and electrical replacement, and removing accessibility barriers.
The schedule for this project has shifted with a goal of bidding this project this fall to be under contract by early 2027. Expect intermittent parking lot closures once the contractor is mobilized at the site in Spring 2027.
Location
Dahl Playfield, 7700 25th Ave. NE, Seattle, WA 98115
Budget
Seattle Parks and Recreation provides $1.78 million for planning, design, and construction.
Schedule
Design & Permitting: July 2026
Bidding: Fall 2026
Construction: Winter 2027 - Summer 2027
Completion: Late Summer 2027