Department of Transportation Scott Kubly, Director
About Us|Contact Us

Services 

Projects 

Planning 

Resources 

Events

News

Site Index

SEATTLE AREA CONSTRUCTION LOOK AHEAD

Last Update: December 1, 2016

To view this information geographically, visit SDOT's Travelers Information Map

Click here to download the PDF of this information

HIGHLIGHTS

December 2: The 30th annual Great Figgy Pudding Caroling Competition will close streets around Westlake Center.

December 2 & 3: Westbound SR520 closed between Bellevue and Montlake Blvd.

December 2 - 4: 23rd Ave. & E. Union St. intersection closed.

December 4: Seattle Seahawks host the Carolina Panthers at 5:30PM at CenturyLink Field.

December 9 - 12: SR520 closed in both directions between Bellevue and Montlake Blvd.

Note: Information subject to change. Additional construction or events may be planned in the Seattle area.
Questions? Contact: construction.coordination@seattle.gov or call 206-684-ROAD


Downtown Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
December 2
6PM - 8:30PM
Great Figgy Pudding Caroling Competition 30th annual Great Figgy Pudding Caroling Competition at Westlake Center.  Event will close Pine St. between 7th Ave. and 4th Ave. (7th Ave. and 6th Ave will remain open), and 5th Ave. between Olive Way and Pike St.
December 3
7AM - 9PM
2nd Ave. closed between Lenora St. and Virginia St. 2nd Ave. will be fully closed between Lenora St. and Virginia St. during removal of a tower crane.
December 3
8AM - 11AM
Lane closures on Western Ave. at Eagle St. Northbound Western Ave. will be closed at Eagle St. during crane work.  One southbound lane will also be closed.
Dec 9 9PM
to
Dec 10 5PM
4th Ave. closed between Lenora St. and Blanchard St. 4th Ave. will be fully closed between Lenora St. and Blanchard St. during a large concrete mat pour.
December 10
5AM - 9PM
Boren Ave. closed between Stewart St. and Howell St. Boren Ave. will be fully closed between Stewart St. and Howell St. during removal of a tower crane.
December 11
8AM - 11AM
Jingle Bell Run Annual fundraising event for the Arthritis Foundation.  Event starts and finishes on Pine St. adjacent to Westlake Park.
September 6
to
January 2017
Seattle City Light Project -
6th Ave. & Cherry St. Duct Bank Installation Project
Seattle City Light plans to install a duct bank between existing electrical vaults at 6th Ave. and Cherry St.  Crews plan to excavate on the west side of 6th Ave. into the south side of Cherry St.  During the first stage of work, 6th Ave. between Columbia St. and Cherry St. will be reduced to two lanes of traffic (9AM - 3PM on weekdays, and 9AM - 6PM on weekends).  In addition, Columbia St. will be reduced to one lane of traffic between 6th Ave. and 5th Ave. (weekends only). 
Stage 1
February 29
to
Fall 2016
Denny Network project Construction of the Denny substation network will begin on Minor Avenue and on Stewart Street. The contractor plans to begin by installing two large vaults – one on Minor Avenue and one on Stewart Street just south of Minor Avenue. They then plan to connect the vaults with underground duct banks. Work will proceed in this manner down Stewart Street to 6th Avenue. This stage of work is expected to be complete in the third quarter of 2016.
September 19
to
December 31
5PM - 7AM
7th Ave. reduced to one lane between Lenora St. and Westlake Ave. for material and equipment staging.
November 28
to
December 30
7AM - 5PM
7th Ave. fully reduced to one lane between Lenora St. and Westlake Ave. during installation of a new electrical duct bank.
Dec 5 - 9
7AM - 3PM
7th Ave. closed between Lenora St. and Westlake Ave. during installation of a new electrical vault.
December 3 - 31
24/7
West curb lane of Virginia St. between 7th and 8th Ave. will be closed 24/7 for the staging of material and equipment.
November 28
to
December 30
7AM - 3PM
7th Ave. reduced to one lane between Virginia St. and Westlake Ave. during installation of a new electrical vault.
November 14
to
December 9
7AM - 5PM
Southbound Minor Ave. N. closed between Harrison St. and Thomas St. the installation of a new electrical duct bank.
November 28
to
December 2
9AM - 3PM
Eastbound Thomas St. closed at Fairview Ave. N. during potholing for underground utilities.
November 28
to
December 25
24/7
Westbound Harrison St. closed between Boren Ave. N. and Westlake Ave. N. during duct bank work.
April 4 Denny Substation project Pontius Ave. N. permanently closed between Denny Way and John St.
Until further notice
24/7
Crews continue excavating and hauling inside the construction fencing. Work hours are 7AM to 7PM weekdays, and 9AM to 5PM Saturday.
November 28
to
December 18
24/7
Eastbound lanes of John St. closed between Minor Ave. N. and Yale Ave. N. for electrical vault excavation and installation.  One westbound lane will remain open.
November 28
to
December 18
24/7
North half of Minor Ave. N. between John St. and Denny Way closed during electrical vault excavation and installation.  
November 2
to
December 11
Center City Connector Streetcar Project Temporary lane restrictions, parking restrictions, and pedestrian detours on 1st Ave. between S. Jackson St. and Stewart St. during potholing for underground utilities.  This is preliminary work for the Center City Connector Streetcar Project, scheduled to begin in the second half of 2017.  Work hours are 9AM to 3PM weekdays, and 9AM to 5PM weekends.
May 23
to
Fall 2017
24/7
Yesler Bridge Rehabilitation Project The Seattle Department of Transportation will be rehabilitating the Yesler Way Bridge, located at the intersection of Yesler Way and Terrace St over 4th Ave S, starting as soon as May 2016 and lasting through fall 2017.  Traffic impacts will include: Yesler Way closed in both directions between 3rd Ave. and midway between 5th Ave. and 6th Ave; Terrace St. closed to through traffic, open to local access; 4th Ave. will have ongoing lane closures and occasional full nighttime and weekend closures; sidewalks on either side of 4th Ave. will have alternating closures; transit and bicycle detours in the project area.
November 4
through
early Spring 2017
24/7
Crews will close the left lane of 4th Ave. S. between S. Washington St. and Jefferson St. during the Yesler Bridge rehabilitation.  In addition, the center lane of 4th Ave. S. will be closed between 9AM and 3PM weekdays.  Travel lanes on the east side of the roadway will remain open during this time.
Until further notice
24/7
Elliott Bay Seawall Project Traffic on Alaskan Wy. S./Alaskan Wy. will be shifted to beneath the Viaduct between S. King St. and Pike St.  Traffic will also be shifted to the east side of Alaskan Wy. between Pike St. and Virginia St.
Until further notice
24/7
As seawall construction expands to the area adjacent to Colman Dock, ferry access for bicyclists and vehicles will shift to Yesler Wy.  Pedestrian access will be maintained via the Marion St. pedestrian bridge, and at street-level between Marion and Columbia St.
Until further notice
24/7
The Marion St. driveway at the Colman Dock shifts north, between Marion St. and Madison St.  During this time most vehicles will exit Colman Dock at Yesler Wy.  All trucks over 30' must exit at Yesler Wy.  Vehicular traffic directed to exit at the Marion St. driveway will turn right or left onto Alaskan Wy.  
October 5 2015
to
June 30 2016
Construction resumes on the waterfront between University St. and Madison St.
January 4
to
mid-2017
Seawall construction begins between Pine and Pike Streets.  Impacts include: removal of on-street parking and trees between Virginia St. and Pike St; removal of the sidewalk on the west side of street; installation of a water treatment facility at Virginia St. and Alaskan Wy.  Access to the Seattle Aquarium, Waterfront Park, and businesses will remain open.
Until Further Notice SR 99 Tunnel Project Parking under the Alaskan Way Viaduct is permanently closed between S King St and Pike St.
Until Further Notice Alaskan Way S.  is closed between S Atlantic St and Madison St until further notice.  Two-way traffic has been re-routed under the Alaskan Way Viaduct and Railroad Way S via 1st Ave S.
Until the SR 99 Tunnel opens to traffic 6th Ave N is closed between Thomas St and Republican St.  Harrison St is closed between Aurora Ave N and Broad St.  Republican St is closed between Aurora Ave N and 6th Ave N.
Until Further Notice 505 Madison St.
Madison Centre

SW corner of 5th & Madison
37-story office tower

Estimated completion: Sept. 2016
Intermittent sidewalk and curb lane closures on the east side of 5th Ave. between Madison St. and Marion St, on the south side of Madison St. from 5th east to the alley, and on the north side of Marion St. from 5th east to the alley.
Until Further Notice 811 5th Ave.
The Mark

NW corner of 5th & Columbia
43-story high rise tower

Estimated completion: April 2017
24/7 closure of sidewalk and curb lane on the west side of 5th Ave. between Marion St. and Columbia St, and on the north side of Columbia St. between 5th Ave. and 4th Ave.  Closure of west travel lane on 5th between Marion and Columbia during working hours.
Until Further Notice 204 Pine St.
2nd Ave. between Pine and Stewart
40-story apartment building
Opening: 2017
Construct 40-story tower.  Intermittent closure of sidewalk and curb lane on the east side of 2nd Ave. between Stewart St. and Pine St, and on the north side of Pine St. between 2nd Ave. and 3rd Ave.  The alley to the east will also be closed.
Until Further Notice
24/7
2301 6th Ave.

707 residential units with ground-floor retail.

Opening: 2015
Intermittent sidewalk, curb lane, and traffic lane closures on  the east side of 5th Ave. between Battery St. and Bell St, the south side of Battery St. between of 5th Ave. and 6th Ave, the north side of Bell St. between of 6th Ave. and 5th Ave, and the west side of 6th Ave. between Bell St. and Battery St.
Until Further Notice
24/7
2021 7th Ave.
2101 7th Ave.

Block 14 & 19
Intermittent sidewalk, curb lane, and traffic lane closures on 7th Ave. between Lenora St. and Westlake Ave, on Lenora St. between of 7th Ave. and 6th Ave, on 6th Ave. between Lenora St. and Virginia St, on Virginia St. between 6th Ave. and Westlake Ave, on Westlake Ave. between 7th Ave. and Westlake Ave, and on Blanchard St. between 6th Ave. and 7th Ave.
Until Further Notice 1901Western Ave.
MarketFront

Retail space and apartment building
Sidewalk, curb lane, and southbound travel lane on the west side of Western Ave, south of Pine St, closed for construction activities.
East Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
Dec 2 7PM
to
Dec 4 10AM
23rd Ave. & E. Union St. intersection closed Crews will close the intersection of 23rd Ave. and E. Union St. while repaving the roadway.  Traffic in the southbound direction will be reopened at 7PM on Saturday, December 3rd.
Dec 2 & 3
11PM - 7AM
Westbound SR520 closed between Bellevue and Montlake Blvd. Crews will close westbound SR520 between Bellevue and Montlake Blvd. during the installation of new bridge decking.  The bicycle and pedestrian path on the floating bridge will also be closed.
December 3
10:30AM - 12PM
Our Lady of Guadalupe, Mother of Americas Celebration SPD will escort a procession from St. Mary's Church to St. James Cathedral.
December 3
1PM - 3PM
Seattle Women March Against Hate March from Volunteer Park to Cal Anderson Park via Broadway.  SPD will escort the march.
Dec 9 11PM
to
Dec 12 5AM
SR520 fully closed between Bellevue and Montlake Blvd. Crews will close SR520 in both directions between Bellevue and Montlake Blvd. during  the removal of the remaining portions of the old westbound SR520 off-ramp to Lake Washington Blvd.  The bicycle and pedestrian path on the floating bridge will also be closed.
January 2015
Through
Summer 2017
WSDOT I-90 Two-Way Transit and HOV Operations - Stage 3 Project will add an HOV lane in each direction of the outer roadway between Seattle and Mercer Island; build an eastbound HOV direct access exit ramp at Island Crest Way on Mercer Island; Upgrade I-90 tunnels fire and life safety systems in Seattle and Mercer Island; prepare the center roadway for Sound Transit's 14-mile East Link rail extension from Seattle to Redmond.
Until further notice
9PM - 5AM
Intermittent nighttime lane closures on eastbound and westbound I-90 between I-5 and Bellevue during dowel bar retrofit.
June 2015
to
Spring 2017
23rd Ave. Corridor Project
Phase 1 - S. Jackson St. to E. John St.
A Seattle Department of Transportation project that will improve safety and mobility for drivers, pedestrians and transit riders. The project includes: modifying 23rd Ave. from a four-lane street to a three-lane street - one lane in each direction with a center left-turn lane (key intersections will stay four lanes); repaving 23rd Ave;
widening sidewalks to at least five feet and repairing broken and buckling sidewalks; installing new streetlights; upgrading traffic signals to give transit priority at key locations; consolidating bus stops to improve transit speed; replacing a 100 year-old water main that runs underneath 23rd Ave. 
Zone A
June 2016
Work on 23rd Ave. between E. Yesler Wy. and E. Cherry St. is now restored to two-way traffic.  Some intermittent work is still required to complete work on Zone A, including additional sidewalk work, pole installation, electrical work, and landscaping.
Zone B
July 27 2016
Work on 23rd Ave. between E. Cherry St. and E. Union St. is now restored to two-way traffic.  Some intermittent work is still required to complete work on Zone B, including additional sidewalk work, pole installation, electrical work, and landscaping.
Zone C
June 1 2016
to
early 2017
Northbound traffic lanes on 23rd Ave. closed between E. Union St. and E. John St. while crews install new storm drains, and replace the street and sidewalks.  Northbound traffic will be detoured to Martin Luther King Jr. Way.  Southbound traffic will be reduced to one lane.
North Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
November 28
to
December 2
10AM - 2PM
Intermittent southbound lane closures on Aurora Ave. N. between Raye St. and Thomas St. Crews will intermittently close the right lane of southbound Aurora Ave. N. between Raye St. and Thomas St. during electrical inspections.
November 30
to
December 2
10AM - 2PM
Intermittent southbound lane closures on Aurora Ave. N. between Raye St. and Mercer St. Crews will intermittently close the right or left lane of southbound Aurora Ave. N. between Raye St. and Mercer St. during electrical work.
December 1
8PM - 6AM
Southbound lane closures on Aurora Ave. N. between Raye St. and Dexter Way off-ramp Crews will close the two left lanes of southbound Aurora Ave. N. between Raye St. and the Dexter Way N. off-ramp during work on an overhead electrical sign.
December 5 - 9
10AM - 2PM
Intermittent southbound lane closures on Aurora Ave. N. between Raye St. and Mercer St. Crews will intermittently close the right or left lane of southbound Aurora Ave. N. between Raye St. and Mercer St. during electrical work.
December 8
8PM - 6AM
Southbound lane closures on Aurora Ave. N. between Raye St. and Dexter Way off-ramp Crews will close the two left lanes of southbound Aurora Ave. N. between Raye St. and the Dexter Way off-ramp during work on an overhead electrical sign.
Until Further Notice 1301 Dexter Ave. N.
Leeward

296-unit apartment building

Opening: 2017
Intermittent sidewalk, parking lane, and bike lane closures on the west side of Dexter Ave. N. between Lee St. and Comstock St.
Northeast Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
Dec 2 & 3
11PM - 7AM
Westbound SR520 closed between Bellevue and Montlake Blvd. Crews will close westbound SR520 between Bellevue and Montlake Blvd. during the installation of new bridge decking.  The bicycle and pedestrian path on the floating bridge will also be closed.
Dec 9 11PM
to
Dec 12 5AM
SR520 fully closed between Bellevue and Montlake Blvd. Crews will close SR520 in both directions between Bellevue and Montlake Blvd. during  the removal of the remaining portions of the old westbound SR520 off-ramp to Lake Washington Blvd.  The bicycle and pedestrian path on the floating bridge will also be closed.
Until further notice Sound Transit
Northgate Link Extension Project
Northgate Station
Parking is temporarily removed on the west side of 1st Ave. NE between NE 92nd St. and NE 95th St.
Until further notice The North Seattle Park-and-Ride lot and interim Park-and-Ride lot located near the former Marie Callender's restaurant in Northgate will close Monday, March 17.  The new interim Park-and-Ride will be located at the NW corner of NE 103rd St. and 5th Ave. NE.
October 1
through
2019
Sound Transit
Northgate Link Extension Project
Roosevelt Station
NE 66th St. and NE 67th St. between 12th Ave. NE and Roosevelt Wy. NE closed to through traffic.  The sidewalk and parking lane on the west side of 12th Ave. NE between NE 65th St. and NE 68th St. will also be closed.
Through
2020
Sound Transit
Northgate Link Extension Project
University District Station
Brooklyn Ave. NE closed between NE 45th St. and NE 43rd St.  NE 43rd St. closed between Brooklyn Ave. NE and the alley to the west.  NE 43rd St. eastbound only between Brooklyn Ave. NE and the alley to the east.
September 2015
to
Summer 2017
SR520 West Approach Bridge North Project 24th Ave. E. overpass closed to pedestrians and bicyclists during project.
6PM - 5AM
Until further notice
Intermittent nighttime flagging on East Lake Washington Blvd. between Montlake Blvd. E. and 24th Ave. E. during girder deliveries.  
9PM - 5AM
Until further notice
Parking restrictions on the south side of East Lake Washington Blvd. between Montlake Blvd. E. and 24th Ave. E. during girder deliveries.  
9PM - 5AM
Until further notice
Intermittent nighttime rolling slowdowns on eastbound SR520 on-ramp from Montlake Blvd. during girder deliveries.  
Northwest Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
SODO Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
December 4
5:30PM - 8:30PM
Seattle Seahawks vs. Carolina Panthers At CenturyLink Field.  Go Hawks!
December 9
8PM - 11PM
Louis C.K. Concert At WaMu Theater.
December 15
5:30PM - 8:30PM
Seattle Seahawks vs. Los Angeles Rams At CenturyLink Field.  Go Hawks!
November 2
to
December 11
Center City Connector Streetcar Project Temporary lane restrictions, parking restrictions, and pedestrian detours on 1st Ave. between S. Jackson St. and Stewart St. during potholing for underground utilities.  This is preliminary work for the Center City Connector Streetcar Project, scheduled to begin in the second half of 2017.  Work hours are 9AM to 3PM weekdays, and 9AM to 5PM weekends.
May 23
to
Fall 2017
24/7
Yesler Bridge Rehabilitation Project The Seattle Department of Transportation will be rehabilitating the Yesler Way Bridge, located at the intersection of Yesler Way and Terrace St over 4th Ave S, starting as soon as May 2016 and lasting through fall 2017.  Traffic impacts will include: Yesler Way closed in both directions between 3rd Ave. and midway between 5th Ave. and 6th Ave; Terrace St. closed to through traffic, open to local access; 4th Ave. will have ongoing lane closures and occasional full nighttime and weekend closures; sidewalks on either side of 4th Ave. will have alternating closures; transit and bicycle detours in the project area.
November 4
through
early Spring 2017
24/7
Crews will close the left lane of 4th Ave. S. between S. Washington St. and Jefferson St. during the Yesler Bridge rehabilitation.  In addition, the center lane of 4th Ave. S. will be closed between 9AM and 3PM weekdays.  Travel lanes on the east side of the roadway will remain open during this time.
Until further notice
24/7
Elliott Bay Seawall Project Traffic on Alaskan Wy. S./Alaskan Wy. will be shifted to beneath the Viaduct between S. King St. and Pike St.  Traffic will also be shifted to the east side of Alaskan Wy. between Pike St. and Virginia St.
Until further notice
24/7
As seawall construction expands to the area adjacent to Colman Dock, ferry access for bicyclists and vehicles will shift to Yesler Wy.  Pedestrian access will be maintained via the Marion St. pedestrian bridge, and at street-level between Marion and Columbia St.
Until further notice
24/7
The Marion St. driveway at the Colman Dock shifts north, between Marion St. and Madison St.  During this time most vehicles will exit Colman Dock at Yesler Wy.  All trucks over 30' must exit at Yesler Wy.  Vehicular traffic directed to exit at the Marion St. driveway will turn right or left onto Alaskan Wy.  
October 5 2015
to
June 30 2016
Construction resumes on the waterfront between University St. and Madison St.
January 4
to
mid-2017
Seawall construction begins between Pine and Pike Streets.  Impacts include: removal of on-street parking and trees between Virginia St. and Pike St; removal of the sidewalk on the west side of street; installation of a water treatment facility at Virginia St. and Alaskan Wy.  Access to the Seattle Aquarium, Waterfront Park, and businesses will remain open.
Until Further Notice SR 99 Tunnel Project Parking under the Alaskan Way Viaduct is permanently closed between S King St and Pike St.
Until Further Notice Alaskan Way S.  is closed between S Atlantic St and Madison St until further notice.  Two-way traffic has been re-routed under the Alaskan Way Viaduct and Railroad Way S via 1st Ave S.
Until the SR 99 Tunnel opens to traffic 6th Ave N is closed between Thomas St and Republican St.  Harrison St is closed between Aurora Ave N and Broad St.  Republican St is closed between Aurora Ave N and 6th Ave N.
Until Further Notice
24/7
255 S. King St.
(North Lot of CenturyLink Field)

23-story hotel tower (282 rooms) and an 18-story office tower  with retail and parking

Estimated completion: Mid-2017
Construct two towers connected by podium for hotel, office, convention center, parking garage and retail space.
Until Further Notice
24/7
400 S. Jackson St.

120-unit apartment with ground-floor retail

Opening: Q4 2016
Construct 7 story mixed use building.  Intermittent sidewalk and travel lane closure on  the east side of 4th Ave. S. north of S. Jackson St.
Until Further Notice
24/7
450 Alaskan Way S.

8-story office building

Estimated completion: Q3 2017
Construct 8-story office building with ground floor retail.  Intermittent sidewalk, parking lane, and travel lane closures on  the north side of S. King St. between Alaskan Way S. and 1st Ave. S.
Until Further Notice
24/7
589 Occidental Ave. S.
Gridiron Condominiums

11-story/107 units

Estimated completion: Summer 2017
Construct 11-story condominiums with ground floor retail.  Intermittent sidewalk, parking lane, and travel lane closures on  the north side of Railroad Way S. between 1st Ave. S. and Occidental Ave. S, and the west side of Occidental Ave. S, north of Railroad Way S.
West Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
December 3
3PM - 9PM
West Seattle Hometown Holiday Tree Lighting and Night Market events will close SW Alaska St. between California Ave. SW and 42nd Ave. SW from 3PM to 9PM.  Night Market hours are 4PM to 8PM, and Tree Lighting event is 4:30PM to 5:30PM.
August 8
through
November
9AM - 4PM
SW Spokane St. Arterial Paving Project Starting the week of August 8, SDOT will repave and make other improvements along SW Spokane St from Klickitat Ave SW to East Marginal Way S.  Work is expected to take approximately three months to complete.  Impacts include single lane closures during working hours and temporary pedestrian and bike detours.
South Seattle Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
December 3
10:30AM - 12PM
Our Lady of Guadalupe, Mother of Americas Celebration SPD will escort a procession from St. Mary's Church to St. James Cathedral.
Dec 4 11:30PM
to
Dec 5 5AM
S. Columbia Way on-ramp to I-5 closed The S. Columbia Way on-ramp to I-5 will be closed during roadway maintenance.
August 8
through
November
9AM - 4PM
SW Spokane St. Arterial Paving Project Starting the week of August 8, SDOT will repave and make other improvements along SW Spokane St from Klickitat Ave SW to East Marginal Way S.  Work is expected to take approximately three months to complete.  Impacts include single lane closures during working hours and temporary pedestrian and bike detours.
South Lake Union Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
December 2 - 4
show times vary
Pacific Northwest Ballet presents George Balanchine's The Nutcracker At McCaw Hall.
December 3
12:01AM - 9AM
Lane and sidewalk closures on Mercer St. and Fairview Ave. N. The following lanes and sidewalks will be restricted during a large concrete mat pour: eastbound Mercer St. will be reduced to one lane between Boren Ave. N. and Fairview Ave. N; southbound Fairview Ave. N. will be closed between Mercer St. and Republican St; northbound Fairview Ave. N. left-turn lane will be closed between Republican St. and Mercer St; the sidewalk on the south side of Mercer St. will be closed; the sidewalk on the west side of Fairview Ave. N. will be closed.
December 6
3PM - 11PM
107.7 The End Deck the Hall Ball At KeyArena.
December 8 - 11
show times vary
Pacific Northwest Ballet presents George Balanchine's The Nutcracker At McCaw Hall.
December 11
7PM - 10PM
Stevie Nicks Concert At KeyArena.
December 14 - 18
show times vary
Pacific Northwest Ballet presents George Balanchine's The Nutcracker At McCaw Hall.
Stage 1
February 29
to
Fall 2016
Denny Network project Construction of the Denny substation network will begin on Minor Avenue and on Stewart Street. The contractor plans to begin by installing two large vaults – one on Minor Avenue and one on Stewart Street just south of Minor Avenue. They then plan to connect the vaults with underground duct banks. Work will proceed in this manner down Stewart Street to 6th Avenue. This stage of work is expected to be complete in the third quarter of 2016.
September 19
to
December 31
5PM - 7AM
7th Ave. reduced to one lane between Lenora St. and Westlake Ave. for material and equipment staging.
November 28
to
December 30
7AM - 5PM
7th Ave. fully reduced to one lane between Lenora St. and Westlake Ave. during installation of a new electrical duct bank.
Dec 5 - 9
7AM - 3PM
7th Ave. closed between Lenora St. and Westlake Ave. during installation of a new electrical vault.
December 3 - 31
24/7
West curb lane of Virginia St. between 7th and 8th Ave. will be closed 24/7 for the staging of material and equipment.
November 28
to
December 30
7AM - 3PM
7th Ave. reduced to one lane between Virginia St. and Westlake Ave. during installation of a new electrical vault.
November 14
to
December 9
7AM - 5PM
Southbound Minor Ave. N. closed between Harrison St. and Thomas St. the installation of a new electrical duct bank.
November 28
to
December 2
9AM - 3PM
Eastbound Thomas St. closed at Fairview Ave. N. during potholing for underground utilities.
November 28
to
December 25
24/7
Westbound Harrison St. closed between Boren Ave. N. and Westlake Ave. N. during duct bank work.
April 4 Denny Substation project Pontius Ave. N. permanently closed between Denny Way and John St.
Until further notice
24/7
Crews continue excavating and hauling inside the construction fencing. Work hours are 7AM to 7PM weekdays, and 9AM to 5PM Saturday.
November 28
to
December 18
24/7
Eastbound lanes of John St. closed between Minor Ave. N. and Yale Ave. N. for electrical vault excavation and installation.  One westbound lane will remain open.
November 28
to
December 18
24/7
North half of Minor Ave. N. between John St. and Denny Way closed during electrical vault excavation and installation.  
Until Further Notice SR 99 Tunnel Project Parking under the Alaskan Way Viaduct is permanently closed between S King St and Pike St.
Until Further Notice Alaskan Way S.  is closed between S Atlantic St and Madison St until further notice.  Two-way traffic has been re-routed under the Alaskan Way Viaduct and Railroad Way S via 1st Ave S.
Until the SR 99 Tunnel opens to traffic 6th Ave N is closed between Thomas St and Republican St.  Harrison St is closed between Aurora Ave N and Broad St.  Republican St is closed between Aurora Ave N and 6th Ave N.
24/7
Until further notice
WSDOT North Access Project Sidewalk on east and west side of Aurora Ave. N. closed between Harrison St. and Mercer St.
24/7
Until further notice
Republican St. closed between Aurora Ave. N. and Dexter Ave. N.  Local Access from Dexter Ave. N. to alley only.
24/7
Until further notice
Westbound Republican St. closed between Dexter Ave. N. and Aurora Ave. N.  Local Access to King 5 driveway only.
Until Further Notice
24/7
1101 Westlake Ave. N.

6-story office building

Opening: December 2015
24/7 closure of west sidewalk and adjacent southbound travel lane for construction activities.
Until Further Notice
24/7
400 Dexter Ave. N.

11-story office building with ground floor commercial space

Opening: 2017
Intermittent sidewalk, curb lane, and traffic lane closures on the east side of Dexter Ave. N. between Republican St. and Harrison St, on the south side of Republican from Dexter Ave. N. east to the alley, and on the north side of Harrison St. from Dexter Ave. N. east to the alley.
Until Further Notice
24/7
435 Dexter Ave. N.

294 unit apartment building in a 7-story building

Opening: 2016
Intermittent sidewalk, curb lane, and traffic lane closures on the west side of Dexter Ave. N. between Republican St. and Harrison St.
Until Further Notice
24/7
222 Fairview Ave. N.

7-story apartment building with retail space

Opening: 2017
Intermittent sidewalk, curb lane, and traffic lane closures on the east side of Fairview Ave. N. between Thomas St. and John St., the north side of John St. east of Fairview Ave. N, and the south side of Thomas St. east of Fairview Ave. N.
Until Further Notice
24/7
221 Minor Ave. N.

7-story apartment building with retail space

Opening: 2017
Intermittent sidewalk, curb lane, and traffic lane closures on the west side of Minor Ave. N. between Thomas St. and John St., the north side of John St. west of Minor Ave. N, and the south side of Thomas St. west of Minor Ave. N.
Until Further Notice
24/7
300 Boren Ave. N. - Troy Block

Two office building with retail space and underground parking

Opening: 2017
Intermittent sidewalk, curb lane, and traffic lane closures on the streets bounded by project: Fairview Ave. N, Thomas St, Boren Ave. N, and Harrison St.
Through
December 2015
400 Boren Ave. N.

Estimated completion: December 2015
Intermittent sidewalk, curb lane, and traffic lane closures on  the east side of Boren Ave. N. between Republican St. and Harrison St, and the south side of Republican St. east of Boren Ave. N.
Until Further Notice
24/7
400 Fairview Ave. N.

13 floor office building with ground-floor retail and 5 floors of underground parking.

Opening: 2016
Intermittent sidewalk, curb lane, and traffic lane closures on  the east side of Fairview Ave. N. between Republican St. and Harrison St, on the south side of Republican east of Fairview, and on the north side of Harrison east of Fairview.
Until Further Notice
24/7
500 Fairview Ave. N.

BioMed Realty Research Center

Opening: 2016
Intermittent sidewalk, curb lane, and traffic lane closures on  the east side of Fairview Ave. N. north of Republican St, and the north side of Republican St. east of Fairview Ave. N.
Until Further Notice
24/7
501 Fairview Ave. N. - Urban Union

12-story office and retail space, with parking for 375 vehicles

Opening: 2016
Intermittent sidewalk, curb lane, and traffic lane closures on  the west side of Fairview Ave. N. north of Republican St, and the north side of Republican St. west of Fairview Ave. N.
SR 99 Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
November 28
to
December 2
10AM - 2PM
Intermittent southbound lane closures on Aurora Ave. N. between Raye St. and Thomas St. Crews will intermittently close the right lane of southbound Aurora Ave. N. between Raye St. and Thomas St. during electrical inspections.
November 30
to
December 2
10AM - 2PM
Intermittent southbound lane closures on Aurora Ave. N. between Raye St. and Mercer St. Crews will intermittently close the right or left lane of southbound Aurora Ave. N. between Raye St. and Mercer St. during electrical work.
December 1
8PM - 6AM
Southbound lane closures on Aurora Ave. N. between Raye St. and Dexter Way off-ramp Crews will close the two left lanes of southbound Aurora Ave. N. between Raye St. and the Dexter Way N. off-ramp during work on an overhead electrical sign.
December 5 - 9
10AM - 2PM
Intermittent southbound lane closures on Aurora Ave. N. between Raye St. and Mercer St. Crews will intermittently close the right or left lane of southbound Aurora Ave. N. between Raye St. and Mercer St. during electrical work.
December 8
8PM - 6AM
Southbound lane closures on Aurora Ave. N. between Raye St. and Dexter Way off-ramp Crews will close the two left lanes of southbound Aurora Ave. N. between Raye St. and the Dexter Way off-ramp during work on an overhead electrical sign.
Until Further Notice SR 99 Tunnel Project Parking under the Alaskan Way Viaduct is permanently closed between S King St and Pike St.
Until Further Notice Alaskan Way S.  is closed between S Atlantic St and Madison St until further notice.  Two-way traffic has been re-routed under the Alaskan Way Viaduct and Railroad Way S via 1st Ave S.
Until the SR 99 Tunnel opens to traffic 6th Ave N is closed between Thomas St and Republican St.  Harrison St is closed between Aurora Ave N and Broad St.  Republican St is closed between Aurora Ave N and 6th Ave N.
24/7
Until further notice
WSDOT North Access Project Sidewalk on east and west side of Aurora Ave. N. closed between Harrison St. and Mercer St.
24/7
Until further notice
Republican St. closed between Aurora Ave. N. and Dexter Ave. N.  Local Access from Dexter Ave. N. to alley only.
24/7
Until further notice
Westbound Republican St. closed between Dexter Ave. N. and Aurora Ave. N.  Local Access to King 5 driveway only.
I-5 / I-90 / SR520 Planned Construction / Events
Date(s) and Times Project Name / Agency Description of Traffic Impacts
Dec 2 & 3
11PM - 7AM
Westbound SR520 closed between Bellevue and Montlake Blvd. Crews will close westbound SR520 between Bellevue and Montlake Blvd. during the installation of new bridge decking.  The bicycle and pedestrian path on the floating bridge will also be closed.
Dec 4 11:30PM
to
Dec 5 5AM
S. Columbia Way on-ramp to I-5 closed The S. Columbia Way on-ramp to I-5 will be closed during roadway maintenance.
Dec 9 11PM
to
Dec 12 5AM
SR520 fully closed between Bellevue and Montlake Blvd. Crews will close SR520 in both directions between Bellevue and Montlake Blvd. during  the removal of the remaining portions of the old westbound SR520 off-ramp to Lake Washington Blvd.  The bicycle and pedestrian path on the floating bridge will also be closed.
December 11
8AM - 11AM
Jingle Bell Run Annual fundraising event for the Arthritis Foundation.  Event starts and finishes on Pine St. adjacent to Westlake Park.
January 2015
Through
Summer 2017
WSDOT I-90 Two-Way Transit and HOV Operations - Stage 3 Project will add an HOV lane in each direction of the outer roadway between Seattle and Mercer Island; build an eastbound HOV direct access exit ramp at Island Crest Way on Mercer Island; Upgrade I-90 tunnels fire and life safety systems in Seattle and Mercer Island; prepare the center roadway for Sound Transit's 14-mile East Link rail extension from Seattle to Redmond.
Until further notice
9PM - 5AM
Intermittent nighttime lane closures on eastbound and westbound I-90 between I-5 and Bellevue during dowel bar retrofit.
September 2015
to
Summer 2017
SR520 West Approach Bridge North Project 24th Ave. E. overpass closed to pedestrians and bicyclists during project.
6PM - 5AM
Until further notice
Intermittent nighttime flagging on East Lake Washington Blvd. between Montlake Blvd. E. and 24th Ave. E. during girder deliveries.  
9PM - 5AM
Until further notice
Parking restrictions on the south side of East Lake Washington Blvd. between Montlake Blvd. E. and 24th Ave. E. during girder deliveries.  
9PM - 5AM
Until further notice
Intermittent nighttime rolling slowdowns on eastbound SR520 on-ramp from Montlake Blvd. during girder deliveries.  




Have the Seattle Area Construction Look Ahead delivered to your inbox

E-mail:

Subscribe (Join the list)

Unsubscribe (Remove me from the list)

Home | About Us | Contact Us | Site Index | News | FAQs | E-Mail Alerts