3rd Ave Belltown Paving Project (Virginia St to Broad St)

3rd Ave Paving Project

What's happening now?

Paving between Blanchard and Battery streets: This area is the last section of major roadway paving across the corridor. Crews are currently working in the center lanes south of the Bell St intersection, and anticipate completing paving activities in those lanes during the week of November 27.

There will be no construction activities on Thursday, November 24 or Friday, November 24 in observance of the Thanksgiving holiday. Crews will resume work on Monday, November 27.

Ongoing side street closures (through early December):

  • Blanchard St between 2nd and 3rd avenues
  • Bell St between 3rd and 4th avenues  

Ongoing minor electrical, pavement, and sidewalk repairs: Crews will continue to perform minor repairs along the entire project corridor through the end of the project, including curb ramp upgrades at the intersections of Wall, Vine, and Clay streets.

Questions? Want to receive project updates?

Email the project team: 3rdAvePaving@seattle.gov
Email updates: Sign up using the form to the right
Text updates: Text "3rdAvePaving" to 33222 to receive construction alerts via text
Call: (206) 920-7073

Detour Map
click on image to view larger

Construction overview

To minimize the duration of the work in front of a given property or block, we divided the project area into 4 work zones. Crews have completed major construction in one zone before moving to the next:

  • Zone A: Virginia St to Blanchard St (major construction complete)
  • Zone B: Blanchard St to Battery St (crews are working here now)
  • Zone C: Battery St to Vine St (major construction complete)
  • Zone D: Vine St to Broad St (major construction complete)

3rd Ave will generally remain open to traffic throughout construction, although it will be reduced to a single lane in each direction in the active construction zone. Occasional detours are expected and will continue to be communicated in advance. On-street parking will be restricted temporarily at construction locations.

Weekend work will be necessary at intersections heavily used by Metro during the week. Other construction will occur during standard work hours (Monday through Friday, 7 AM – 5 PM). SDOT is working closely with King County Metro so buses continue to operate during construction, although individual bus stops will be temporarily closed or moved. We will not simultaneously close bus stops next to one another.

Project overview

3rd Ave through Belltown is a primary arterial carrying some 3,600 vehicles per day, approximately 45% of which are buses. Currently, the street has many potholes and patches from previous cuts into the pavement to install utilities.

Prior to this project, the street was composed of a mix of concrete panels and asphalt. We are removing all asphalt and replacing it with concrete panels, which last longer than asphalt. We are also replacing concrete panels in the existing curb lane where needed, specifically broken panels and/or those that have previously been cut into for repairs or utility service connections (which makes them more susceptible to breaking).

In addition to repaving the street, the project includes:

  • Replacing curb ramps at some intersections to bring them into compliance with the Americans with Disabilities Act (ADA). Sidewalks will otherwise not be impacted.
  • Replacing and/or repairing sections of water mains and sewer lines
  • Installing electrical conduit at select locations
  • Expanding both the northbound and southbound bus zones at Virginia St in order to better accommodate the large number of buses using these stops

Schedule

Construction began May 2, 2017 and take approximately 10 months to complete, with major paving completed this year.  We will update this page as construction progresses.  

Contact information

We're committed to keeping you informed and working with neighbors to limit construction impacts to the extent feasible. Here are some ways to get more information about the project:

  • Subscribe for project email updates by using the form above.
  • Contact us directly with questions about the project 3rdAvePaving@seattle.gov or call at (206) 920-7073
  • Text "3rdAvePaving" to 33222 to sign up for construction alerts via text
  • Request a briefing for your business or organization (contact us via phone or email)

Community Outreach Lead
Paul Elliott

Project Manager
Brian Glas 

Funding

The estimated cost of this project is $9.3 million, with funding from the voter-approved Move Seattle Levy.

Materials

Updated: 11/16/2017