8th Ave S Sidewalk Improvements

Updated: September 24, 2020

What's happening now?

The new sidewalks are open! 8th Ave S now has new sidewalks on both sides of 8th Ave S between S Sullivan St and S Southern St.

Before and After

Maybe you've seen these yard signs in the neighborhood. This is to let neighbors know about extending the street designs next to the South Park Library up 8th Ave S. See below for details and please contact us with questions.

Sign

Sign Spanish

Project Overview

We built new sidewalks on 8th Ave S between S Sullivan St and S Southern St in South Park in 2020. This included a new sidewalk on the east side of the street where a temporary in-street walkway was installed in 2016 and a replacement of the existing sidewalk on the west side.

The SDOT design team worked closely with our SDOT Urban Forestry team and was able to preserve the beautiful street trees on both sides of the street. The sidewalk now meets current Americans with Disabilities Act (ADA) standards, making it easier and safer for people of all ages and abilities to walk to destinations like the South Park Community Center, South Park Library, and local businesses.

DECORATIVE STREET DESIGNS ON 8TH AVE S

Based on positive feedback about the decorative crosswalks and street designs on 8th Ave S and S Cloverdale St, we're planning to extend similar art up 8th Ave S between S Cloverdale and S Southern streets. The art would be painted at the same locations as the existing painted curb bulbs with an additional decorative crosswalk at 8th Ave S and S Cloverdale St and potential painting on the new sidewalks. See this fact sheet for details and please contact us with questions.

8th Ave Art

Background

Over several years the existing sidewalk was harmed because of growing tree roots damaging the pavement. Based on feedback from neighbors, we made efforts to save the trees while preserving parking and maintaining access for people walking. This led to the creation of the existing temporary walkway. We were able to allocate funding to construct a permanent sidewalk and replace the sidewalk on the west side of the street as well.  

Existing sidewalk

Existing temporary walkway that we'll make into a permanent sidewalk with this project

Project Area

New/replaced sidewalks on both sides of 8th Ave S in South Park between S Southern St and S Sullivan St.

Map

Schedule

2018-2019: Design and outreach (including door-to door, project 'walk and talk,' and attending community meetings)

June-August 2020: Sidewalk construction

Following sidewalk construction: Install decorative street designs (timing TBD based on weather and crew availability)

Community Outreach

Date Description
August 2020 Posted yard signs about art
Summer 2020 Regular listserv email updates 
June 2020 Mailer to project neighbors
February 19, 2019 Project info at South Park Street Projects Open House
September 12, 2018 8th Ave S Sidewalk Improvements Walk-through
July 30, 2018 Door-to-door to adjacent neighbors on 8th Ave S
Early summer, 2018 Presentations to various community groups

Funding

This project is funded by the 9-year Levy to Move Seattle. We selected this project for funding because it scored highly on the Pedestrian Master Plan, which aims to improve safety along the walking routes to schools and transit.

Materials

Need translation?

If you need this information translated, please call 206-257-2201.

如果您需要此信息翻譯成中文 請致電 206-257-2201.

Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa 206-257-2201.

Si necesita traducir esta información al español, llame al 206-257-2201.

Odeeffannoon kun akka siif 206-257-2201.

Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi 206-257-2201.

የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ 206-257-2201.

ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ 206-257-2201.

당신이 번역이 정보를 필요로하는 경우에, 206-257-2201 로 전화 해주십시오.