S Columbian Way / S Alaska Street Paving Project

Updated: July 9, 2018

What’s happening now?

Thank you to all the neighbors, business owners, and community groups that have engaged with the project over the last several months. We are still working to finalize the construction schedule with the contractor. At this point, we expect construction to begin mid-to-late July 2018.

Once crews start working, they will begin with storm drain and curb ramp work in select locations. Construction for this project, along with Wilson Ave S and Swift Ave S / S Myrtle St / S Othello St projects, will likely extend into summer 2019.

We’ll be sending regular construction updates including schedule information before work begins.

Project Overview

S Columbian Way / S Alaska St between Beacon Ave S and Martin Luther King Jr Way S is a two-way arterial serving southeast Seattle. This stretch of road provides an important connection for all commuters between Beacon Hill and Rainier Valley. Our goal is to improve the safety, accessibility, and comfort for all users.

This year, we plan to start work to repave about 1 mile of S Columbian Way / S Alaska St between Beacon Ave S and Martin Luther King Jr Way S. As part of the repaving, we will be taking off the old top layer of the road, placing new asphalt and repainting the lane lines. In addition to repaving, we will also be putting in a new protected bike lane along this stretch of road between Beacon Ave S and Martin Luther King Jr Way S.

Other improvements include:

  • Installing or upgrading curb ramps to be compliant with the Americans with Disabilities Act (ADA)
  • Replacing traffic detection loops that control the signals
  • Repairing and replacing some sections of sidewalk in the project area
  • Building a pedestrian refuge island at the intersection of S Alaska St and S Alaska Pl

map of Columbia Way project

cross section view of lanes with one sidewalk, planting strip, bike lane, buffer and travel lane in each direction.

For more information about out 2018 paving projects, visit Current Paving Projects.

Project Schedule*

2016

Initial design and outreach

Spring - Summer 2017

Updated design

Community outreach continues

Fall 2017

Final design

Late 2017

Advertise for construction

Summer 2018

Construction begins

*This schedule if a rough estimation of the project timeline. The schedule is subject to change.

Funding

Total project budget: $2.02 million
Funding Sources:

  • SDOT’s Arterial Asphalt and Concrete Program
  • Sidewalk Safety Repair Program
  • Levy to Move Seattle

Outreach To Date

FormatDocument/DescriptionDate
Flyer Spring 2018 fact sheet Spring 2018
Flyering Southeast business survey collection March 2018
Flyering S Columbian Way / S Alaska St residential flyer December 2017
Mailing Project letter to the community
Mailed to ~200 homes and businesses
August 2017
Flyer May 2017 fact sheet
Distributed to ~500 homes, businesses, and at fairs and festivals
Summer 2017
Email update Southeast cross-section announcement March 2017
Briefing Settle Bike Advisory Board December 2016
Briefing Rainier Vista Traffic Safety Committee December 2016
Flyer Southeast Door Hanger
Distributed to ~500 homes and businesses
November 2016
Email update Southeast Open House Summary November 2016
Open house Southeast Open House Meeting Boards October 2016
Open house Southeast Open House in Columbia City
Close to 30 people signed-in
October 2016
Flyer and email update Southeast Project Fact Sheet October 2016
Flyer Southeast Open House Notice
Distributed to over 500 homes and businesses
October 2016
Email update Southeast Survey Results Summary October 2016
Email update Southeast Survey Results September 2016
Flyer Southeast Paving Survey Notice
Distributed to ~500 homes and businesses
August 2016

Get Involved

If you would like to learn more about the project or would like to request a briefing, please do not hesitate to contact us.