South Park Community Center Stabilization
Updated: January 19, 2021
Early 2021
South Park area projects update: Press releases January 2021 (English; Spanish; Vietnamese)
Community Center Stabilization Work
Construction for this project is expected to begin in late spring 2021 and will occur at the same time as the South Park Community Center Site Redevelopment Project.
South Park Community Center was identified in the 2016 Community Center Strategic plan for a major maintenance project focused on extending the life of the facility and increasing programming potential. A preliminary scope of the project is outlined below. The final scope is expected to be refined throughout the design process based on more information about cost and needs. Seattle Parks and Recreation planning staff are meeting with the community center staff to review the scope and schedule.
Location
South Park Community Center, 8319 8th Ave S, 98108
Budget
$3,370,000 provided by the Seattle Parks District
Schedule
Planning and Design: Fall 2018 - Early 2021
Construction: Late Spring 2021 - Fall 2022
* Construction will occur at the same time as the South Park Community Center Site Redevelopment Project.
Project Description
This project addresses a number of major maintenance, accessibility, and program needs at South Park Community Center. It will include a roof replacement, HVAC system upgrades, renovation of the restrooms, kitchen and lobby spaces in addition to the addition of a gym divider and replacement of the multi-purpose room flooring.