Morgan Junction Park Addition

Updated: July 30, 2025

Summer 2025

Work on removing the hazardous soil from the new parcel, formerly used as a dry cleaner, began in 2024. This work included the demolition of the existing concrete and asphalt, installation of temporary shoring, and excavation to remove the lens of dry-cleaning solvents. Clean fill is being imported, to be followed by topsoil, temporary irrigation, and grass. The team is currently addressing some new permitting issues. 

The remediation work has been more extensive than anticipated, which will impact the subsequent phase(s) of the project. We hope to open the remediated grass area of the park addition to the public in the late fall of this year (Phase I). In the meantime, we are working to value-engineer the expansion design and enable a scaled-down Phase 2 of the park development to proceed, with the hope of securing funding to implement a future Phase 3 for the remaining improvements.  

Additionally, Seattle Parks and Recreation (SPR) is working with community partner Morgan Junction All Wheels Association (MJAWA) to integrate an all-wheels skate-dot into the project during a future phase. MJAWA, alongside Grindline Skateparks, has gathered community input on potential designs. SPR and MJAWA will work towards integrating skate features into the larger project for permitting and construction, dependent on funding availability.

To learn more about the Morgan Junction All Wheels Association, please visit: https://mjawa.org/

Location

The addition parcel is located at 6317 California Ave SW, adjacent to:
Morgan Junction Park, 6413 California Ave SW, 98136 

Budget

Original 2014 Project Budget: $6,360,000
Additional 2025 Funding: $1,200,000
Total Project Budget: $7,560,000

SPR developed a design for the Morgan Junction Park Addition project in 2019 based on community input and engagement. The project was placed on hold in 2020 as part of COVID-related Citywide budget reallocations and was restarted in 2023. Since restarting the project, SPR has been supportive of community-led efforts to install a skatedot on the existing Morgan Junction Park site. Unfortunately, due to cost escalation of the development project, high environmental remediation costs of the park addition site, and citywide budget constraints, SPR had to reconsider which elements could be built with the project to keep it within budget. Even after the addition of $1.2M to the project budget in early 2025, some elements of the original 2019 design, as well as the skatedot on the original park site, cannot be constructed within the current project budget. We are working with the community on an agreement and fundraising plan to construct the mutually desired skatedot.

Schedule

Phase I: Soil Remediation

Permit & Design: 2025, additional permitting ongoing 
Anticipated remediation complete: Late Fall 2025

Phase II: Park Addition 

Permit & Design: Summer 2026
Bid: 
Fall 2026
Anticipated Construction: 
Winter 2026 - Summer 2027

Project Description

In 2014, Seattle Parks and Recreation purchased the .47-acre property at 6311 California Ave SW, north of Morgan Junction Park, to expand the park and provide additional open space for this high-density neighborhood. The design will incorporate accessibility in compliance with the Americans with Disabilities Act (ADA) and additional park elements will be incorporated after gathering public input. A transfer of jurisdiction ordinance is necessary to expand and connect the new site to the existing park, anticipated to be completed in late fall 2025.

This project was put on hold during the pandemic when the City of Seattle turned its focus to essential functions to address the immediate social and economic crisis. In Sept. 2022, the Seattle City Council, acting in their role as Seattle Park District Board, passed a new six-year funding plan for the 2023-2028 Park District cycle, which included funding for this project.

The additional parcel and current Eddy Street ROWwill not be accessible during construction. 

Community Participation

Involvement Opportunity at Morgan Junction Festival - 6/18/2023

Public Meeting and Open House - 6/22/2019

Public Meeting and Open House - 6/16/2018

Seattle Parks and Recreation (SPR) has determined that the project has no probable significant adverse impact on the environment. An environmental impact statement (EIS) is not required under RCW 43.21C.030(2)(c). This decision was made after a review of a completed environmental checklist and other information on file with SPR. This information is available to the public on request. The Determination of Non-Significance was issued on February 22, 2021.

Parks and Recreation

AP Diaz, Superintendent
Mailing Address: 100 Dexter Ave N, Seattle, WA, 98109
Phone: (206) 684-4075
Fax: (206) 615-1813
pks_info@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Parks and Recreation

Healthy People, Thriving Environment, Vibrant Community