Hubbard Homestead Play Area

Updated: January 12, 2024

Early 2024

Modifications to play equipment foundation design in the course of construction necessitated additional design documentation, review, and oversight. To ensure changed footing conditions provide adequate stability it was determined that field inspections by Geotech of record were required. Special inspections were conducted in September with directions to the contractor for the next steps. 

Work on site resumed in the fall and has been proceeding with contractor availability. Parks will provide an updated construction schedule when available. 


View three vendor renderings of the play equipment here and please note the color of the play area surfacing will be green and not black. 

Seattle Parks and Recreation awarded the construction contract to LW Sundstrom Construction for the addition of the play area to Hubbard Homestead Park. Portions of the park adjacent to the new play area will be closed. The majority of the park will remain open for public use. 

The Hubbard Homestead play area project site will be located on the east end of Hubbard Homestead Park. The scope of the project will include minor site improvements and a play area that's in compliance with current play area safety standards and Americans with Disabilities Act (ADA) access. Funding for this park improvement is provided by the Seattle Park District.

Location

Hubbard Homestead Park, 11203 5th Ave NE, 98125

Budget

The Seattle Parks District provides $600,000 in funding for this project.   

Schedule

Planning and Design: Summer 2018 - Fall 2021
Bidding: Fall 2021
Construction: Fall 2022 - TBD

Project Description

This project will develop a play area within the existing Hubbard Homestead Park. The goal is to provide playground equipment which will include play elements and access for children of all ages and abilities. Improvements will include fall surfacing, seating, storm water mitigation and limited landscape improvements. 

As part of this project we will be decommissioning the playground at Victory Creek Park, 1059 NE Northgate Way, Seattle, WA 98125. Unfortunately, playgrounds are not designed and constructed to last forever and this playground was no exception. Under Parks and Recreation policy number 060-P 5.12.1, a decommissioning is necessary because it is substantially out of code compliance. The decommissioning of this playground will allow maintenance resources for a new play area at Hubbard Homestead Park.

Community Participation

Download the meetings posters

Download the online survey results from October 2018

Public Meeting 10/16/2018

Public Meeting 12/4/2018

Public Meeting 2/28/2019

Parks and Recreation

AP Diaz, Superintendent
Mailing Address: 100 Dexter Ave N, Seattle, WA, 98109
Phone: (206) 684-4075
Fax: (206) 615-1813
pks_info@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Parks and Recreation

Healthy People, Thriving Environment, Vibrant Community