Link to Transportation Home Page Link to Transportation Home Page Link to Transportation About Us Page Link to Transportation Contact Us Page
Delivering a first-rate transportation system for Seattle Scott Kubly, Director

Services 

Projects 

Planning 

Resources 

Events

News

Site Index


Street Maintenance Program
Pavement Management
Current Paving Projects
Recent Paving Projects
Bridge Projects
Bridge Painting Projects
Bridge Rehabilitation, Replacement and Seismic Retrofit
Pothole Rangers
Street Maintenance Request Form

3rd Ave Belltown Paving Project (Virginia St to Broad St)

Taking care of basics

Updated June 21, 2017

What’s happening now

Beginning at 6 AM on Thursday, June 22 through Monday, July 31, Blanchard St will be closed to through traffic between 3rd and 4th avenues as crews perform sewer and storm drain repair then repave the street. See details and detour map below.

  • Local vehicle traffic can access Blanchard St via the alley between 3rd and 4th avenues.
  • On-street parking will be restricted in the construction work zone, between the alley and 3rd Ave. However, it will be maintained between the alley and 4th Ave.
  • Pedestrian access will be maintained.
  • Uniformed police officers or flaggers will be present to assist traffic flow when crews are working.
  • Emergency vehicles can access the work zone.
  • The work is expected to create noise, dust, vibration, and concrete odor.
  • Like many of the project’s activities, this work is weather-dependent and subject to change. Updates will be posted if any changes are anticipated.

What else is happening in the project corridor?
Here are details about other anticipated work over the next 2 weeks:

  • Overnight water shut-off between Bell and Lenora streets this Friday: Seattle Public Utilities (SPU) will shut off water between Bell and Lenora streets this Friday, June 23 to perform water line work. Work will begin after 11 PM and be completed overnight. SPU has notified affected properties.  
  • Construction preparation and traffic flow changes between Vine and Broad streets: This week, crews are surveying the area, installing tree protection, and sawcutting the old concrete panels. Sawcutting can be loud, so if you are in the area and have any concerns or questions about the noise, don’t hesitate to get in touch with the project’s outreach team (see below for contact info). Next week, crews will begin removing the existing concrete, starting on the east side of Broad St. Near the work zone, traffic will be reduced to 1 lane in each direction on 3rd Ave and potentially on Clay St to provide crews with sufficient space to work.
  • Vault installation and potholing continues along the corridor: This work involves a small crew (2 to 3 people) working in a small area of the road defined by traffic cones.

Construction on the 3rd Ave Paving Project through Belltown began Tuesday, May 2. The contractor is working between Virginia and Blanchard streets through approximately late July. The bus stop at Virginia St is closed during this time.

Questions? Want to receive project updates?

Email the project team: 3rdAvePaving@seattle.gov
Email updates: Sign up using the form below
Text updates: Text "3rdAvePaving" to 33222 to receive construction alerts via text
Call: (206) 920-7073










Click to view larger


Above: 3rd Ave before construction

Construction overview

To minimize the duration of the work in front of a given property or block, we’ve divided the project area into 4 work zones. Crews will be required to finish major construction in one zone before moving to the next:

  • Zone A:  Virginia St to midblock of Lenora St (crews are working here now)
  • Zone B:  Midblock of Lenora St to Battery St
  • Zone C:  Battery St to midblock north of Vine St
  • Zone D:  Midblock north of Vine St to Broad St

3rd Ave will generally remain open to traffic throughout construction, although will be reduced to a single lane in each direction in the active construction zone. Occasional detours are expected and will be communicated in advance. On-street parking will be restricted temporarily at construction locations.

The water main and sewer line work will require some water shutoffs, which we expect will occur at night, for the least impact. Weekend work will be necessary at intersections heavily used by Metro during the week. Other construction will occur during standard work hours.

SDOT is working closely with King County Metro so buses continue to operate during construction, although individual bus stops may be temporarily closed or moved. We will not simultaneously close bus stops next to one another.

Project Overview

3rd Ave through Belltown is a primary arterial carrying some 3,600 vehicles per day, approximately 45% of which are buses. Currently, the street has many potholes and patches from previous cuts into the pavement to install utilities.

The street is currently composed of a mix of concrete panels and asphalt. We will remove all of the asphalt and replace it with concrete panels, which will last longer than asphalt. We’ll replace existing curb lane concrete panels that are broken or have previously been cut into for repairs or utility service connections (which makes them more susceptible to breaking). 

In addition to repaving the street, the project includes:

  • Replacing curb ramps at some intersections to bring them into compliance with the Americans with Disabilities Act (ADA). Sidewalks will otherwise not be impacted.
  • Replacing and/or repairing sections of water mains and sewer lines. This will require water shutoffs, most likely at night for the least impact.
  • Installing electrical conduit at select locations.
  • Expanding both the northbound and southbound bus zones at Virginia St in order to better accommodate the large number of buses using these stops.

Schedule

Construction began May 2, 2017 and will take approximately 10 months to complete.  We will update this page as construction progresses.

Funding

The estimated cost of this project is $9.3 million, with funding from the voter-approved Move Seattle Levy.

Contact Information

We’re committed to keeping you informed and working with neighbors to limit construction impacts to the extent feasible. Here are some ways to get more information about the project:

  • Subscribe for project email updates by clicking here.
  • Contact us directly with questions about the project 3rdAvePaving@seattle.gov or call at (206) 920-7073
  • Text 3rdAvePaving to 33222 to sign up for construction alerts via text
  • Request a briefing for your business or organization (contact us via phone or email)

Phone line: (206) 920-7073 (calls are answered during weekday work hours, 7 AM to 5 PM, and monitored during night and weekend work)
Email: 3rdAvePaving@seattle.gov

Community Outreach Lead
Paul Elliott

Project Manager
Brian Glas

Materials

Other SDOT projects in the area

  • 2nd Ave Mobility Improvements - We are making traffic signal improvements and extending the existing 2-way protected bike lane along 2nd Ave from Pike St to Denny Way. These improvements will organize the street and move people more efficiently. Construction began in March and will continue through fall 2017.  Visit the project website here to learn more or contact the project hotline at (206) 905-3639.

  • Center City Connector Project - We will join the existing South Lake Union and the First Hill Streetcar lines, largely along 1st Ave through downtown, creating new north-south connections across downtown. Utility relocations are planned to start this summer. We expect to finish streetcar design by 2018 and the new streetcar line to open in 2020. Visit the project website here to learn more or contact the project team at centercitystreetcar@seattle.gov or 206-615-1070.

  • Center City Bike Network - We are studying and prioritizing locations for a protected bicycle lane network in downtown Seattle. This spring we’re talking with the community about how to connect the two-way protected bike lane on 2nd Ave to the new Westlake protected bike lane via Bell St or a combination of Bell and Blanchard streets. Once a concept is finalized, we’ll seek funding and develop a schedule for implementation.
Home | About Us | Contact Us | Site Index | News | FAQs | E-Mail Alerts