Longfellow Creek Natural Drainage System (NDS) Project

Photo of a street with natural drainage system
Example of a natural drainage system.

Project description 

Enhancing Our Communities with Natural Drainage Systems and Pedestrian Improvements 
Seattle Public Utilities (SPU) is constructing natural drainage systems (NDS) at 3 sites in the Longfellow Creek basin. Natural Drainage Systems are built in the roadway shoulder (the space between the street edge and the property line) and are filled with deep-rooted plants and spongy soils that temporarily hold and clean polluted stormwater from streets and sidewalks before the stormwater enters our waterways.

Natural drainage systems offer multiple community benefits, including:

  • Increased landscaping
  • Reduced drainage issues
  • Creation of habitat along our streets
  • Healthier creek ecosystems
  • Traffic calming
  • More street trees
  • Pedestrian improvements

SPU is partnering with Seattle Department of Transportation (SDOT) on this project to provide pedestrian improvements at 24th Ave SW between Thistle and Barton streets and at the SW Kenyon St pedestrian bridge at 24th Ave SW. This project is funded in part by the Levy to Move Seattle. 

Through the City of Seattle's Public Art Program, we're adding artwork at the SW Kenyon St site. The artwork along with the pedestrian improvements and new natural drainage systems are designed to create space for the community to connect with neighbors and the surrounding habitat.

Location

This project includes three locations, which were selected based on a variety of factors that included community input, recurring drainage and flooding issues, and technical feasibility.

  • 24th Ave SW (between SW Thistle and SW Barton St)
  • Sylvan Triangle (Sylvan Way SW between SW Orchard St and Delridge Way SW)
  • SW Kenyon St (near the Longfellow Creek pedestrian bridge at 24th Ave SW)

Visit the site map to see where each of the sites is located in the Longfellow Creek area and see below for more information about the final design and anticipated construction impacts for each of the sites.

SPU is installing a natural drainage system from SW Thistle St to SW Barton St, which will help improve stormwater drainage, slow down traffic, and remove pollutants from stormwater runoff to improve water quality in Longfellow Creek, a salmon-bearing creek.

We know that many residents highly value pedestrian safety and sidewalks, and as part of the project we are excited to partner with SDOT to install a sidewalk along the west side of 24th Ave SW between SW Thistle and SW Barton St.

To view the planned work near your home, please review the Final Design and Info for 24th Ave SW.

What to Expect During Construction?

Construction for this site began in April 2022. Crews began by installing the underground drainage system and completing roadway work. After the underground drainage and roadway work, crews installed natural drainage systems and landscaping.

During construction, residents can expect the following impacts in their neighborhood:

  • Work will generally occur during weekday, daytime hours
  • Construction noise, dirt, dust, and vibrations
  • To minimize disruption, work will generally be done in segments moving along 24th Ave SW
  • Parking restrictions and temporary lane closures near the work area
  • Temporary blockage of driveway access during some construction activities. When possible, the contractor will work to reopen access during nights and weekends.
  • Materials and equipment staged along the road edge near construction activities
  • The contractor will work to maintain access for delivery services, garbage/recycling/compost pick-up, and emergency vehicles. In some instances, mailboxes may be temporarily relocated during construction to facilitate deliveries. 
  • Some residents may experience brief, temporary water service interruptions to facilitate water meter relocation. Advanced notice will be provided prior to planned water outages.
  • Removal of street trees in areas where NDS and sidewalks will be installed and installation of new street trees along 24th Ave SW in accordance with SDOT's Urban Forestry requirement to improve Seattle's tree canopy, which has many benefits, including improving air and water quality. 
  • Installation of curb and gutters and driveway aprons along 24th Ave SW as well as final street pavement restoration, which may require 24-hour/day closures to allow for curing

What to Expect After Construction?

Natural drainage systems are living systems and their appearance will change over time. The grasses, shrubs, and trees installed will grow and change as the garden matures. It may take up to three years for plants and shrubs in the natural drainage system to reach full maturity, and possibly longer for trees. The examples below show what a natural drainage system may look like over time.

Example before construction

Example newly planted

Example growing phase

Example mature phase

Maintenance and Care

SPU is responsible for all maintenance needs of the natural drainage systems, which will include general upkeep of the natural drainage system plantings, checking that the natural drainage system is functioning properly, removing sediment, and replacing or removing plantings and trees in the natural drainage system, if needed. You will not be asked to perform any maintenance of the natural drainage system.

SPU plans to install a large natural drainage system in the public right-of-way on Sylvan Way SW near Home Depot. Work at the site began in October 2022; however, during early construction, crews encountered unanticipated groundwater impacts. Due to technical challenges from these impacts, work at the Sylvan Triangle site will be postponed and completed under another project contract.

To view the planned work at this site, please review the Final Design and Info for Sylvan Way SW.

SPU has partnered with SDOT and the Office of Arts and Culture to develop planned improvements near the intersection of SW Kenyon St and 24th Ave SW. These improvements include:

  • New walkway, bridge, and boardwalk to make it easier for people to get to nearby schools, homes, and bus stops
  • Natural drainage systems to reduce pollution in Longfellow Creek
  • Art installation to enhance the space and connect community to the creek

To view the planned work at this site, please review the Final Design and Info for SW Kenyon St.

What to Expect During Construction?

Construction at this site began in June 2022 but was paused for several months to allow for emergency repairs on a damaged water main near Longfellow Creek. Construction at the site resumed in early summer 2023. 

You can expect the following during construction at this site:

  • Work will generally occur during weekday, daytime hours
  • Construction noise, dirt, dust, and vibrations
  • Parking restrictions and road closures near the work area
  • Closure of the pathway and bridge over Longfellow Creek at 24th Ave SW
  • Pedestrian detours will be in place
  • The project team has notified local schools about construction impacts

What's happening now?

Construction on the Longfellow Natural Drainage System project began in April 2022 and is ongoing.

  • 24th Ave SW Site: Contractor crews have finished installing the natural drainage system and roadway improvements at the 24th Ave SW site. SPU continues to coordinate with property owners on several property-specific work items, which will be completed in early summer 2024.
  • SW Kenyon St Site: Contractor crews have finished installing the natural drainage system and pedestrian improvements at the SW Kenyon St site. Crews will complete minor landscaping work at the site in late spring 2024.

    The public art planned for the corner of 24th Ave SW and SW Kenyon St will be installed in late spring or early summer 2024 in collaboration with Portland-based artist Brian Borrello and the City of Seattle’s Public Art Program.

    Several work items at the SW Kenyon St site will be postponed and completed by another contractor later this year. This work will primarily include underground drainage infrastructure that will be installed along  the north side of SW Kenyon St, west of 24th Ave SW. We’ll be back in touch with more information about when this work will occur.

  • Sylvan Way SW Site: During construction at the site in fall 2022, the project team encountered unexpected underground conditions. Due to technical challenges from these impacts, work at the Sylvan Way SW site will be postponed and completed under a separate project contract in late 2024 or 2025.

Please sign up to receive project email updates to stay informed about this project throughout construction.

Community benefits

This project will improve water quality in Longfellow Creek, as well as improve stormwater drainage, slow down traffic, provide pedestrian improvements, and beautify streets.

The project will also help the City of Seattle achieve its goal of managing 700 million gallons of stormwater runoff using green infrastructure by 2025.

Community engagement

Thank you to everyone who shared their valuable feedback throughout planning and design! We have finalized the project design and have begun construction. 

Please sign up to receive project email updates to stay informed about this project throughout construction.

Through the City's Public Art Program, Portland-based artist Brian Borrello developed an art installation for the SW Kenyon St site.

The artist's goals are to make this place interesting for the community to visit and for the art to offer something unexpected, thought-provoking, and perhaps a little magical. This site is where life forces are nourished by the creek, where neighbors can connect with each other while they pass through, and where community can experience the natural world and its often-unseen processes.

rendering of proposed art

Past work

  • Initial outreach to gather community input to inform site selection
  • Concept development for potential natural drainage systems sites
  • Design development for the three selected sites
  • Design phase community outreach, which included hosting an Online Open House, an online questionnaire, email list updates, mailers, meetings with residents, and more
  • Finalize project design and perform the construction contracting process
  • Pre-construction community outreach which included mailers, drop-in sessions, meetings with residents, and email list updates about anticipated construction timelines and impacts at each site

Spring 2022 to 2024

  • Construction on this multi-site project to occur
  • Provide ongoing construction updates to the community

Natural drainage systems slow stormwater and filter out pollutants before they can harm our creeks and other waterways. Keeping pollutants out of our water is important for fish, aquatic life, and people.

Building a natural drainage system in the Longfellow Creek basin is part of the Plan to Protect Seattle's Waterways. SPU used to call these "roadside rain gardens" but now calls them "natural drainage systems" or "NDS."

Why Longfellow Creek? Longfellow Creek is a salmon-bearing urban creek with degraded water quality adjacent to where people live, work, and play. Stormwater picks up pollutants from streets — including oil, heavy metals, and fertilizers — every time it rains and flows into the creek through ditches or pipes. This project will remove pollutants from the stormwater before it reaches the creek.

Funding information

This project is paid for in part by the King County Flood Control District and the Levy to Move Seattle. Art at the SW Kenyon St site is through the City of Seattle's Public Art Program.

Public Utilities

Andrew Lee, General Manager and CEO
Address: 700 5th Avenue, Suite 4900, Seattle, WA, 98104
Mailing Address: PO Box 34018, Seattle, WA, 98124-5177
Phone: (206) 684-3000
SPUCustomerService@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Public Utilities

Seattle Public Utilities (SPU) is comprised of three major direct-service providing utilities: the Water Utility, the Drainage and Wastewater Utility, and the Solid Waste Utility.