View Ridge Underground Cable Replacement

City Light Undergrounding Project

View Ridge Cable Replacement Construction Project Map

Project Description

Seattle City Light crews are replacing underground electrical infrastructure in the View Ridge neighborhood with new duct banks, conduits, and vaults. Once underground civil construction is complete, crews will install new cables for the electrical distribution system. This work started on March 25, 2025.

Location

Construction will occur in the View Ridge neighborhood of Seattle.

What's Happening Now?

Project Update (April 17, 2025):

Upcoming Work April 17 - 30:

A crew will work at the intersection of NE 77th Street and 58th Avenue NE, moving west around the corner through the south end of 57th Avenue NE.

A second crew will work at the intersection of NE 77th Street and 58th Avenue NE, moving south, and then along NE 75th Street and up 57th Place NE.

Crews will not be working on April 19 or 20.

Intermittent lane closures are expected along all work zones. Please follow traffic flagger directions while moving throughout the work zone where necessary.

Construction for this project includes digging new trenches, placing new conduit for electrical cables, and restoring the trenched area as we work along the project map. When necessary, we will notify affected customers about planned outages required to switch over to the newly installed cables.

Community Benefits

This work will result in enhanced electrical reliability and reduce the likelihood of unplanned power outages in the View Ridge area.

Anticipated Impacts

  • Temporary parking and traffic restrictions. Crews will work to limit traffic impacts and traffic flaggers will be present when needed.
  • Noise from equipment use is expected throughout the project duration.
  • Planned power outages will be required to complete the work safely. We will notify affected residents in advance before any planned power outages.
  • Trenching for conduits will occur in the public right-of-way (e.g., street and planting strips). Crews will cover trenches with steel plates outside of construction work hours. These plates are safe to drive over.
  • All affected streets and landscaping will be restored and repaved, per City of Seattle standards.
  • We will work to reduce interruption to mail, garbage, recycling, and yard waste services as much as possible.
  • Private service connections to homes are not included in this work. The homeowner is responsible for installing conduit in their private property.

Schedule

Construction Start: March 2025
Duration: 4 months
Daily Work Schedule: Monday - Friday, 7 a.m. - 5 p.m. Work may be needed outside of these hours, including on weekends.

City Light

Dawn Lindell, General Manager and CEO
Address: 700 5th Ave, Seattle, WA, 98104
Mailing Address: PO Box 34023, Seattle, WA, 98124-4023
Phone: (206) 684-3000
SCL_ExternalComms@seattle.gov

Seattle City Light was created by the citizens of Seattle in 1902 to provide affordable, reliable, and environmentally responsible electric power to the City of Seattle and neighboring suburbs.