Fairview Ave North Bridge Replacement

Map showing area of Fairview Ave N bridge replacement project

Project Description

Seattle City Light plans to install a temporary second set of power lines along Fairview Avenue North. Crews will temporarily install two new 100-foot steel poles; including their corresponding foundations and power lines to the west of the permanent poles and lines and de-energize the permanent lines. Once the bridge replacement project is complete, City Light crews will remove the temporary poles and foundations and re-energize the permanent lines. SDOT's bridge replacement work began in 2017/2018.

Location

The Fairview Avenue North bridge is located in Seattle's South Lake Union neighborhood.

What's Happening Now?

The temporary steel poles and wiring have been completed prior to the beginning of SDOT's Fairview Bridge Replacement Project. Once the existing bridge has been replaced, City Light intends to remove the temporary steel poles and overhead conductor wiring.

Community Benefits

  • The work is necessary to assure safe electrical clearance distances and system reliability during the Seattle Department of Transportation's (SDOT) project to replace the aging Fairview Avenue North Bridge.

Anticipated Impacts

  • Public use of the space (including parking) near the location of the temporary steel poles will not be permitted during construction.
  • No power outages are anticipated at this time. If outages are necessary, customers will be notified in advance.
  • August 2016 - Shaft foundations for two temporary steel poles were installed.
  • April 2017 - City Light Crews will install two temporary steel poles and temporary transmission (115 kV) and distribution (26 kV) lines.
  • TBD - Temporary poles, transmission and distribution lines removed, and original lines re-energized.

  • Construction Start: August 2016
  • Duration: Until 2020-2021
  • Daily Work Schedule: Mon-Fri, 8:30 a.m. - 4:30 p.m.

William Chin
Seattle City Light Project Manager
William.chin@seattle.gov
(206) 684-7977

Adonis Ducksworth
SDOT Communications and Outreach Lead
fairviewbridge@seattle.gov
(206) 775-8715

Click here to view the project website