Arroyo Conduit Installation

Map showing area of work in the Arroyo neighborhood

Project Description

Underground, direct buried cables in the Arroyo neighborhood are approaching the end of their useful life and will require new electrical conduits and cables. Seattle City Light has identified several areas within the Arroyo neighborhood that will require installing new conduits, vaults, and other associated work. Streetlights will also be replaced as part of this work.

Location

Crews are working in the Arroyo and Arbor Heights neighborhoods in southeast Seattle.

What's Happening Now?

Project Update (July/August 2021): 

  • Electrical crews are preparing to install primary cables and equipment at several utility vault locations within the construction work area. 
  • Streetlight crews have installed the circuits that will power the new lights. Crews will install new streetlight bases, poles and fixtures on streets in the work area shown on the map above. 
  • This remaining work is estimated to take up to six months to complete and will require planned outages. City Light will notify affected customers in advance of any planned outage.
  • Customers can expect some traffic impacts during this work. Crews will use appropriate street control measures as needed depending on the street type.
  • The City of Seattle sets regulations based on national standards for roadway lighting to maintain safe driving conditions and pedestrian safety. It is City Light's responsibility to follow those standards. After careful assessment, City Light determined additional lighting was required to provide proper lighting conditions in Arroyo/Arbor Heights. Some areas may receive additional lighting as part of this project.
  • Please be aware that due to the nature of our work maintaining the electrical system, some essential tasks require crew members to work closely together for their safety. We ask that residents continue to adhere to social distancing guidelines when walking near a construction site. The safety of our customers and crews is our number one priority.
  • This work is in accordance with protocols in place to meet all COVID-19 guidelines from the Centers for Disease Control and Prevention, Washington State Department of Health, and Occupational Safety and Health Administration.

Community Benefits

  • This work will result in enhanced electrical reliability and efficiency.

Anticipated Impacts

  • City Light crews will be working in multiple locations at a time. Customers can expect temporary parking and traffic restrictions. Crews will work to limit traffic impacts.
  • Maintenance power outages are required to do the work safely. Affected residents will be notified in advance before any outage.
  • Trenching for conduits will occur in the public right-of-way (e.g. street and planting strips). Some sidewalk and driveway aprons will be affected. Trenches will be covered with steel plates or fenced off outside of construction work hours.
  • City Light crews will work closely with Seattle Department of Transportation's (SDOT) Urban Forestry group to ensure the protection of trees. SDOT staff may be onsite to monitor this work.
  • All affected areas will be restored and repaved, in accordance with SDOT guidelines.
  • Individual electrical service connections to new developments (homes/buildings) are not included in this work. The homeowner is responsible for installing conduit in their private property. Learn more at seattle.gov/city-light/construction-services.
  • The City of Seattle sets regulations based on national standards for roadway lighting to maintain safe driving conditions and pedestrian safety. It is City Light's responsibility to follow those standards. After careful assessment, City Light determined additional lighting was required to provide proper lighting conditions in Arroyo/Arbor Heights. Some areas may receive additional lighting as part of this project.
  • Crews will be installing 3000K LED streetlights in several areas. The Cleveland style streetlight fixture will be installed in smaller, residential streets. The Arieta fixture will be installed along Marine View Drive. These installations are anticipated to occur after civil construction is completed. See photos below:

Examples of the streetlights that will be installed in the Arroyo area

  • Construction Start: May 2018
  • Duration: Until 3rd quarter 2021
  • Daily Work Schedule: Mon-Fri, 9 a.m.-3 p.m.; weekends 9 a.m.-6 p.m. Some evening work may be required.

Thomas Gravell
Electrical Service Representative Supervisor
thomas.gravell@seattle.gov
(206) 386-1672 
 
Sign up for email updates on the Arroyo Conduit Installation Project: http://ow.ly/2CMx30iN0eo