Timeline

If you are interested in receiving updates about the project schedule, please sign up for the project listserv.

Mid to Late 2018

  • Project team worked on design and permitting
  • Community outreach about the project

Early to Mid 2019

  • Continue working on project design

Late 2019

  • Finalize design and start preparing for construction
  • Provide project update to the community

Early 2020

  • Pre-construction community notification and outreach
  • Construction work is scheduled to begin as soon as March 2020
  • Construction is expected to take 6 to 10 months
  • Continuing updating the community, as needed, during construction

*Tentative schedule as of November 2019 assuming that there are no project delays due to the permitting process, weather, or other factors.