Master Use Permit Renewals

What Is It?

A renewal extends the life of a land use / master use permit (MUP) from 3 years to 5 years. You can renew a master use permit if: 

  • Your current permit hasn’t expired
  • Your project meets the land use and environmental codes that are current when you submit your renewal request

You don’t need to renew your land use permit if you have applied for a building permit before your MUP expires. The MUP assumes the life of the building permit.

How Much Does It Cost?

The fee to apply for a renewal is the SDCI base fee. In addition, the review fee is twice the land use hourly fee and covers up to 2 hours of review. We will bill additional review hours at our hourly rate.

How Long Does It Take?

We try to issue renewal permits within two weeks.

Steps to Get a Renewal

Request your renewal online at the Seattle Services Portal.
 

Construction and Inspections

Nathan Torgelson, Director
Address: 700 5th Ave, Suite 2000, Seattle, WA, 98104
Mailing Address: P.O. Box 34019, Seattle, WA, 98124-4019
Phone: (206) 684-8600
Phone Alt: Violation Complaint Line: (206) 615-0808
Contact Us

Newsletter Updates

Subscribe

Sign up for the latest updates from Construction and Inspections

SDCI issues land use, construction, and trade permits, conducts construction and housing-related inspections, ensures compliance with our codes, and regulates rental rules. SDCI is committed to an antiracist workplace and to addressing racism through our work in the community.