Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
Seattle Parks and Recreation Seattle Parks and Recreation Home Page Seattle Parks and Recreation - About Us Seattle Parks and Recreation - Contact Us
Christopher Williams, Acting Superintendent.
  Parks   Centers & Pools Activities Reservations & Permits Projects & Planning A - Z Index
 
Parks Legacy Plan
Partnerships
Parks and Green Spaces Levy
Acquisition
Development
Environment
Opportunity Fund
Oversight Committee
Pro Parks Levy
Community Center Levy
Major Maintenance
Neighborhood Matching Fund
Horticulture
Sustainable Building & Development
City-Wide Planning Documents
Plans for Individual Parks
Parks Standards
Policies and Agreements
Requests for Proposals
Requests for Qualifications
Board of Park Commissioners
Seattle Parks Foundation
Seattle Conservation Corps
Parks Preservation Work Group
Seattle Parks and Recreation

Jefferson Park Golf Course Facility Renovations
Project Information

 

Location: 4101 Beacon Ave S, Seattle WA 98108


Project Status

March 2014
The old clubhouse was demolished in late 2013 and construction of the new facility is underway.

The long awaited project will feature a new clubhouse with a double decked covered and heated driving range, an enlarged and improved food & beverage operations with indoor and outdoor facilities, banquet and meeting rooms, enlarged pro shop with club repair, new teaching facilities and new putting greens.

During the construction period golf operations will move to temporary facilities across Beacon Ave. behind the existing first tee. A pro shop and a food service facility will be set up in order to continue to offer as many services and amenities possible. There will be no impact upon the 18-hole course which will remain open throughout construction. Efforts are being made to keep partial use of the driving range available to golfers during construction. However, logistical issues must be overcome before a firm decision can be made.

The new clubhouse will provide a improvement to municipal golf services and a wonderful community space to non-golfing patrons as well.


LOCATION
4101 Beacon Ave S, Seattle 98108
BUDGET
$7,283,686 is allocated for planning, design and construction

2011 Multi Purpose Limited Tax General Obligation Debt
Ordinance #123442
SCHEDULE
Planning: March 2011 - June 2011
Design: July 2011 - September 2013
Construction: November 2013 - December 2014
Completion: December 2014

Project Description

This project provides improvements to the Jefferson Golf Course facilities, including but not limited to, an all new clubhouse and banquet room, driving range expansion to accommodate a second deck, new electric cart barn, cart path improvements, possible parking expansion and landscaping renovations.

Parks staff briefed the Golf Steering Committee (GSC) on Nov 10, on the preferred schematic design and reductions in the project scope so as to stay within the projects budget. The revised scope includes the following elements:
  1. Clubhouse Two-story with banquet hall, caf and outdoor dining, Pro-shop, teaching space
  2. Double-deck Driving Range improved lights and netting
  3. Modified cart barn capacity for 40 gas carts, with the potential for future expansion and/or conversion to electric carts
  4. Modified cart paths limited to surrounding the cart barn, Beacon Ave, 1st Tee and 18th Hole, additional path paving as an Add Alternate
  5. Modified parking plan
    • Increase parking behind the clubhouse to 20 stalls
    • Reduce the parking on the short nine by half, with the remaining parking as an Add Alternate
The GSC approved the revised project scope.


Community Participation

Public Meeting #1  10/13/11

Public Meeting #2  12/15/11

Design Commission Presentation #2  2/2/12


Important Links


*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.

 
Updated March 11, 2014

Events

Currently no events are scheduled.

For More Information

Toby Ressler
800 Maynard Ave S, Suite 300
Seattle, WA 98134-1336
206-615-1482
toby.ressler@seattle.gov

New Clubhouse South View
New Clubhouse South View