Late Spring 2022

This project has experienced some unforeseen delays; however, construction documents are in progress. The plans are being revised to include the play equipment replacement at Westcrest Park. Both projects will be bid together for construction by the same contractor. We anticipate the bid advertisement in summer 2022, with construction starting in fall 2022.

Location

Lincoln Park, 8011 Fauntleroy Way SW, 98136

Budget

Seattle Park District provides $600,000 for planning, design and construction.

Schedule

Design: Spring 2021 - Spring 2022
Bid Advertisement: Summer 2022
Construction: Fall 2022

Project Description

This improvement project is funded by the Seattle Park District. The play area renovation will update play equipment with play structures accessible to children of all ages and abilities. Additionally, accessibility improvements that meet the standards from the Americans with Disabilities Act (ADA) will be made throughout the play area.

Community Participation

Public Meeting 11/29/2017