Major Maintenance Project Information
Hiawatha Playfield Field Renovation
Address:
2700 California Ave SW; Seattle, WA 98116-2451
Current Status
June 2009
Parks issued a notice to proceed to Contractor Premier Fields on June
15, 2009.
The current construction schedule extends into November 2009. Parks
will provide schedule updates as the work progresses.
December 2008
In July 2008 Parks submitted the Type V Master Use Permit (MUP) Application
to the Department of Planning and Development to allow the replacement
of the field light poles at Hiawatha Playfield with up to 90 height.
The track and athletic field is currently illuminated with 10 light
poles ranging in height from 55 to 84. The replacement lighting
system is designed to limit spill light and glare by raising the floodlight
mounting heights from the code maximum of 30 to a height of 70
to 90.
Seattle City Council approved the land use permits for the work.
Project Description
Budget:
$3,600,000
Funding sources:
Seattle Parks and Recreation, $2.5 million
Seattle Public Schools, $1 million
King County Council (Dow Constantine), $100,000
Construction begins:
Summer 2009
Project complete:
Winter 2009
The Hiawatha Playfield will be renovated with synthetic turf and updated
lighting. Baseball, soccer, and football will be represented with full-sized
facilities. Three lanes of a non-conforming rubberized track will encompass
the sports field. Each lane will be 3.5 feet in width. The existing
field events located on the east side of the Community Center will also
be renovated.
Hiawatha Playfield is an Olmsted park and as such any changes to its
existing condition must be reviewed and approved by the Landmarks Board
and its subcommitte -- the Architectural Review Committee (ARC). ARC
has reviewed the concept twice in the past few months and the full Landmarks
Board will likely review the project details sometime in February 2008.
The football grid will be minimally striped with boundary and 5 yard
lines.
When Olmsted designed the Playfield in 1911, he only needed to accomodate
baseball: football, in its infancy, was primarily played at the college
level, and soccer wasn't yet recognized in America. Now, almost 100
years later, those three sports (plus track) must fit into the space
as it was created from Olmsted's original design.
In order to accomplish this so that the sports fields are optimally
oriented, the single, signficantly large elm located at the south end
of the existing soccer field, must come down. This elm suffered storm
damage in 2003 and is susceptible to Dutch Elm disease. As the elm will
likely suffer additional impacts during the pending field construction,
it is prudent to remove the tree now rather than compromise the fields'
orientation.
In recent years 13 young trees were installed within the inside of
the existing track. These trees will either be moved or replaced elsewhere
depending on their value.
Community Involvement
Public Meeting
*
Note: To view this document, you must have the Adobe Acrobat
Reader installed on your system. If you already have the Reader installed,
select the file above. If you don't have the Reader, you can get it
at the Adobe
web site for free.
Updated
June 19, 2009
|