Seattle.gov Home Page
Seattle.gov This Department
Seattle Parks and Recreation Seattle Parks and Recreation Home Page Seattle Parks and Recreation - About Us Seattle Parks and Recreation - Contact Us
Christopher Williams, Acting Superintendent.
  Parks   Centers & Pools Activities Reservations & Permits Projects & Planning A - Z Index
 
Parks Legacy Plan
Partnerships
Parks and Green Spaces Levy
Pro Parks Levy
Community Center Levy
Major Maintenance
Neighborhood Matching Fund
Horticulture
Sustainable Building & Development
City-Wide Planning Documents
Plans for Individual Parks
Parks Standards
Policies and Agreements
Requests for Proposals
Requests for Qualifications
Board of Park Commissioners
Seattle Parks Foundation
Seattle Conservation Corps
Parks Preservation Work Group
Seattle Parks and Recreation

Major Maintenance Project Information
Discovery Park - Waterline Replacement and North Parking Lot Restoration

 

Address: 3801 Discovery Park Blvd; Seattle, WA 98199


Current Status

April 2012
Andy Sheffer of Seattle Parks and Recreation and John Rundle of WR Consulting presented project details and gathered community comments at a public meeting held on April 10, 2012. Their presentation and the Q & A from the meeting can be found below.

Andy will also present this information at the upcoming West Point Citizens Advisory Council meeting on Wednesday, April 18. See Events for details.

Project planning and design runs from Jan - June 2012.

Project Description

Budget: Funding provided per the West Point Settlement Agreement
Construction begins: 7/1/2012
Project complete: 12/2012

WATER LINE REPLACEMENT
Approximately 800 feet of the 8” water main along Kansas Ave that connects to the existing main in the intersection at the south and north ends of the road is being replaced. The existing east-west main between Kansas Ave and the valve assembly will serve as a carrier pipe for a new 2” service line to the Theater site area, and will supply several quick couplers.

Removal of the remaining service drive paving to the Theater site and restoration is planned. Restoration will consist of the removal of existing utilities and surface features, minor grading, and relocation of bollards. Areas of planting will be identified.

NORTH PARKING LOT MODIFICATIONS
Removal of the west bound lane of the access roadway along the north side of the parking area is proposed to eliminate erosion to the ravine below. The area will be regraded to form a shallow swale for bioretention and water quality treatment of stormwater runoff, and a mulch or gravel path added. The roadway transition from the intersection at the east end of the pavement will be modified to accommodate the removal.

The parking lot modifications include the repair and removal of deteriorated paving and repairs to the storm drain outfall. Areas where the pavement is removed will be restored. The design for the failing drainage outfall and flume on the north side of the road will consist of either a pipe with a portion installed on the surface, or channel modifications consisting of log step-down for a more natural system, or a combination of these two schemes.


Community Involvement


Public Meeting 4/10/2012

*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.

 
Updated April 18, 2012

More Information

Andy Sheffer
Seattle Parks and Recreation
800 Maynard Ave S
Suite 300
Seattle WA 98134
206-684-7041
e-mail

Events

West Point Citizens Advisory Council

Wednesday, April 18, 2012
6:30 - 8:00 p.m.
Discovery Park Visitor's Center
3801 Discovery Park Blvd Seattle, WA 98199

Andy Sheffer of Seattle Parks will present information about the Waterline Replacement and North Parking Lot Modifications during the West Point Advisory Council Meeting. This meeting is open to the public.