| BUDGET |
$635,000 from the Parks and Green Spaces Levy for planning, design and construction.
|
| SCHEDULE |
Planning: Spring 2011
Design: Spring 2011 - Fall 2013
Construction: January 2013 - May 2013
Completion: May 2013
|
Identified in the Parks and Green Spaces Levy this renovation project provides for the conversion of the existing wading pool into a spraypark.
The design team will work with the community through a series of public meetings to develop a recommended design of possible spray features for the wading pool conversion. Consideration will be given to ADA accessibility, as well as long-term maintenance, operation costs and sustainable design.
Public Meeting #1 5-25-11
*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.
Currently no events are scheduled.
Kelly Goold
800 Maynard Ave S
Suite 300
Seattle, WA 98134
206-684-0586
kelly.goold@seattle.gov
|
Concept C Layout Plan Equipment Plan Select an image to enlarge |
|
|
| Home | Partnerships | Park Board | Volunteer | FAQ | Parkways |
|
|