Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
Seattle Parks and Recreation Seattle Parks and Recreation Home Page Seattle Parks and Recreation - About Us Seattle Parks and Recreation - Contact Us
Christopher Williams, Acting Superintendent.
  Parks   Centers & Pools Activities Reservations & Permits Projects & Planning A - Z Index
 
Parks Legacy Plan
Partnerships
Parks and Green Spaces Levy
Acquisition
Development
Environment
Opportunity Fund
Oversight Committee
Pro Parks Levy
Community Center Levy
Major Maintenance
Neighborhood Matching Fund
Horticulture
Sustainable Building & Development
City-Wide Planning Documents
Plans for Individual Parks
Parks Standards
Policies and Agreements
Requests for Proposals
Requests for Qualifications
Board of Park Commissioners
Seattle Parks Foundation
Seattle Conservation Corps
Parks Preservation Work Group
Seattle Parks and Recreation

Highland Park Playground
Spraypark Conversion
Parks and Green Spaces Levy
Project Information

 

Location: 1100 SW Cloverdale St, Seattle WA 98106


Project Status

Thank you Seattle!
Seattle Parks and Recreation opened the Highland Spraypark in late June 2013.

Parks presented the final design for this new spraypark to the community in March 2012 and construction began in early 2013.

Parks selected SiteWorkshop as the design consultant for this project. Together they presented spray features and design ideas at the first public meeting held on May 25, 2011. Approximately 35 West Seattle residents came out to discuss spray park features and how those features could best fit Highland Park.

The Levy originally allocated $200,000 for this project. Through the community initiated Opportunity Fund process, the Levy Oversight Committee became aware that this project needed additional funding. The project received additional funding from the Levy inflation. This will allow for full water re-circulating systems and provide a better play experience and water conservation.


LOCATION
1100 SW Cloverdale St, Seattle WA 98106
BUDGET
$635,000 from the Parks and Green Spaces Levy for planning, design and construction.
SCHEDULE
Planning: Spring 2011
Design: Spring 2011 - Fall 2013
Construction: January 2013 - June 2013
Completion: June 2013

Project Description

Identified in the Parks and Green Spaces Levy this renovation project provides for the conversion of the existing wading pool into a spraypark.

The design team will work with the community through a series of public meetings to develop a recommended design of possible spray features for the wading pool conversion. Consideration will be given to ADA accessibility, as well as long-term maintenance, operation costs and sustainable design.


Community Participation

Public Meeting #1 5-25-11


Important Links


*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.

 
Updated September 19, 2013

Events

Currently no events are scheduled.

For More Information

Kelly Goold
800 Maynard Ave S
Suite 300
Seattle, WA 98134
206-684-0586
kelly.goold@seattle.gov

Concept C
Concept C
You will need adobe acrobat reader to view this document.

Layout Plan
Layout Plan
You will need adobe acrobat reader to view this document.

Equipment Plan
Equipment Plan