Major Maintenance Project Information
Miller Playfield Field
Address:
330 19th Ave. E, 98112
Current Status
Thank you Seattle this project is complete!
The community celebrated the opening of this field on Saturday, September 19, 2009 with a bountiful potluck dinner and ice-cream social. Over 100 community members and field users attended.
The notice-to-proceed was issued on June 1, 2009 to Precision Earthworks. Construction has progressed per schedule.
Project Description
Budget:
$2,200,000 for planning, public involvement process, design, bidding
and construction.
Construction begins:
Summer 2009
Project complete:
Late Fall 2009
This project replaces the existing sand field with synthetic turf at Miller Playfield, and performs other related work. Planning and design is funded in 2008 and the Department will seek construction funding in 2009. This project was requested by the community through the Community Capital Suggestion Process and is also part of a six-year plan to renovate ballfield lighting and fields throughout the parks system. This renovation will meet Park recreational needs and neighborhood plans and input, City Codes, and Department standards.
Community Involvement
Public Meeting - 11/05/08
*
Note: To view this document, you must have the Adobe Acrobat
Reader installed on your system. If you already have the Reader installed,
select the file above. If you don't have the Reader, you can get it
at the Adobe
web site for free.
Updated
October 14, 2009
|