Greenwood Park Addition

Updated: June 25, 2019

Summer 2019

Thank you to everyone for your feedback on the preferred schematic plan. We heard from many of you that the plan needed a skate element and we have included that update with skate benches to the north of the sport court. We also have added a hillside slide that will connect the play area to the upper park. 

View schematic plan here

The new additions pushed the schedule slightly. We are finalizing our construction documents and anticipate starting construction this summer.

Seattle Parks and Recreation staff thank everyone who attended the three 2018 meetings and participated in the online survey. Your input, feedback and ideas were very useful. Meeting and survey documents are available below.

The Greenwood Park Addition project is located at 8805 Fremont Avenue N, 98103. With community support, Seattle Parks and Recreation purchased the additional property in 2013 to provide additional open space for the community.

Location

Greenwood Park, 8805 Fremont Ave N, 98103

Budget

The Seattle Park District provides $463,050 for planning, design and construction.

Schedule

Planning: Fall 2017 - Early Winter 2017/18
Design: Spring - Fall 2018
Construction: Summer 2019 - Winter 2019/20

Project Description

Seattle Parks and Recreation purchased this .1 acre site at 8809 Fremont Ave N. in 2013 to provide more open space for the growing neighborhood and expand the existing Greenwood Park. The Seattle Park District provides funding for the development of this parcel and the extension of Greenwood Park. Seattle Parks and Recreation will work with the community to design the park space. The design will incorporate accessibility features in compliance with the Americans with Disabilities Act (ADA).

Community Participation

Off Leash Area Announcement

Public Meeting and Open House 2/13/2018

Public Meeting and Input Opportunity 6/2/2018

Public Meeting and Input Opportunity 8/15/2018