Seattle.gov Home Page
Seattle.gov This Department
Seattle Parks and Recreation Seattle Parks and Recreation Home Page Seattle Parks and Recreation - About Us Seattle Parks and Recreation - Contact Us
Christopher Williams, Acting Superintendent.
  Parks   Centers & Pools Activities Reservations & Permits Projects & Planning A - Z Index
 
Parks Legacy Plan
Partnerships
Parks and Green Spaces Levy
Acquisition
Development
Environment
Opportunity Fund
Oversight Committee
Pro Parks Levy
Community Center Levy
Major Maintenance
Neighborhood Matching Fund
Horticulture
Sustainable Building & Development
City-Wide Planning Documents
Plans for Individual Parks
Parks Standards
Policies and Agreements
Requests for Proposals
Requests for Qualifications
Board of Park Commissioners
Seattle Parks Foundation
Seattle Conservation Corps
Parks Preservation Work Group
Seattle Parks and Recreation

Bell Street Park
Parks and Green Spaces Levy
Project Information

 

Location: First to Fifth Avenue


Project Status

April 2014
Seattle Parks and Recreation is happy to announce completion of the Bell Street Park project. The opening celebration will be held Saturday, April 12 from 2 to 5 p.m. All are welcome!

The project took longer than anticipated to complete as it is impacted by Puget Sound Energy's work on the tunnel project. Parks anticipates the remaining block to be completed soon. Thank you for your patience.

Parks awarded the construction contract to AGR Construction Inc. for Bell Street Park. The park will run from 1st through 5th Ave. on Bell Street. The contractor is dividing the work into individual blocks.

Construction Schedule

  • Block 1 (1st 2nd) substantially completed
  • Block 2 (3rd 4th) substantially complete
  • Block 3 (4th 5th) construction began July 29 - complete early 2014
  • Block 4 (2nd 3rd) substantially complete

Parks and the contractor are working to minimize the impacts on the community; construction on three blocks may overlap during late summer and early fall. Seattle Parks is providing safe access to all businesses and residents along this portion of Bell Street during construction.

Thank you for your patience and cooperation during construction. Please contact the project manager, Patrick Donohue with any concerns or questions during project construction.

AGR Construction of Monroe WA was the low bidder and met all bidder qualifications. The contract award is $3,377,000.

The Parks and Green Spaces Levy funds the entire four blocks of the park from 1st Avenue to 5th Avenue on Bell Street.

We have successfully negotiated a Memorandum of Agreement with other City agencies that spells the responsibilities of each agency for the long term maintenance of Bell Street Park.

This project transforms four blocks of Bell Street into a 56,000 square foot new street park. The continuous level pavement will encourage pedestrians, cyclists, and automobiles to share the space.

The work is limited to the following blocks; 1st to 2nd, 2nd to 3rd, 3rd to 4th, and 4th to 5th. No work shall take place in the 1st, 2nd, 3rd, 4th, and 5th avenues right-of-ways or where there may be a City of Seattle Department of Transportation paving moratorium in place.

The existing street lights will be removed and replaced with an average of 5 energy efficient LED street lights and 10 energy efficient 14 foot pedestrian lighting fixtures per block. This new lighting raises the ambient light level and is designed to minimize light pollution.

After changes in the licensing requirements for outdoor restaurant dinning Parks adjusted the design to accommodate and encourage outdoor dining for all existing restaurants in the corridor and proposed restaurant on Bell at 2nd.

The trees along Bell Street will be removed. This is an issue the City does not take lightly. Specific tree information can be found here. Parks did an extensive review of the existing trees within the four blocks of the proposed Bell Street Park. An element of the tree replacement plan is Parks staff and the project design team will be developing a long-term tree management plan covering maintenance, pruning and replacement of the trees over the next 30 years for the Bell Street corridor.

Thank you for your attendance and participation in the Bell Street Park public meetings. Parks presented an update at the Best of Belltown on June 14, 2011 for the Belltown Business Association and neighborhood residents.

Together Seattle Parks and Recreation and the Office of Arts and Cultural Affairs is happy to announce the selection of Sheila Klein as the project artist for Bell Street Park. She is a nationally recognized public artist that has worked from Los Angeles to Pittsburgh.

Sheila will work with project designers and city staff to develop site-specific artwork consistent with the goals of the project. It is hoped that the art will be the catalyst for park activation. The artwork development schedule will follow the design and construction schedule for the park. The artwork is commissioned with Parks and Green Spaces Levy 1% for Art funds.

The third meeting for the park development in May 2010 was well attended. The design team presented a hybrid design that was developed with community input from the previous meeting. Please see presentation below.

Over 130 people attended the second public meeting held on January 13, 2010. The designers, SvR + Hewitt, presented two different design options that took their inspiration from the history of the area and a lighting specialist presented information on light levels on Bell.

The design team walked the audience through a comparison of the options requesting input on the “Sluiced Surface” option and the “Measured Movement” option. The community offered positive feedback and direction for the design of the park. The community encouraged the designers to look into a combination of the two designs emphasizing the importance of safety, activation, lighting, and using green / recycled materials.

In October 2009 Seattle Parks selected SvR + Hewitt as the primary design consultant for this project. Four Belltown blocks, from First to Fifth Avenues will be turned into Seattle's first park boulevard with swales and natural landscaping.

The conceptual design was approved by the Parks Levy Oversight Committee in April 2009 for $3.5 million in funding based on its ability to provide 17,000 square feet of much-needed open space for the Belltown Community.

The conceptual design was subsequently presented to the City Council in June 2009. They approved both the funding authority and a transfer of jurisdiction of the Bell Street right-of-way to Parks so that the plan could be implemented as envisioned.


LOCATION
First to Fifth Avenue
BUDGET
$3.5 million from 2008 Parks and Green Spaces Levy. An additional $1.5 million of funding from the acquisition fund will be applied to this project upon approval from City Council in March 2013.
SCHEDULE
Planning: Summer 2009 - Spring 2010
Design: Summer 2010 - Winter 2012
Construction: January 2013 - February 2014
Completion: March 2014

Project Description

The neighborhood of Belltown holds a unique spot within the City on many levels. Geographically it links other neighborhoods: the waterfront, Pike Place Market, downtown, Seattle Center, and the Denny Triangle. It has an eclectic mix of businesses, residents, and architecture. It is a dedicated, caring, and inclusive community that not only supports, but also embraces more than 30 human services agencies and low-income housing located there.

Belltown is one of the highest density neighborhoods. From 1990 to 2005 the number of housing units increased by more than 246% and it is expected to grow by another 30% by 2010.

Per the City’s goals for open space, the neighborhood should have 8.64 acres of open space now, and 13.34 by 2024. Unfortunately, the land and resources dedicated to open space has not kept pace with this growth in both residential and business use. Belltown has one park (Regrade Dog Park) that is about one-half acre, clearly falling short of providing for basic needs, let alone establishing the livable, pedestrian-oriented and active mixed-use neighborhood visualized in the neighborhood plan and by the City.

Long term aggressive planning for additional open space in the form of parks and green relief is needed. However, there is an immediate need to provide pedestrian amenities that a great neighborhood like Belltown deserves.

The project was first proposed in the 1998 Belltown Neighborhood Plan, and has been endorsed by a range of community organizations – including Belltown Housing and Land Use Committee and the Bell Town Community Council.

The project converts one traffic lane and reconfigures parking to create a park like corridor through the heart of Belltown. The four block area will be improved with landscaping, better lighting, and more open space.

 


Community Participation

Property Owner Meeting 11-09-09
Public Meeting 11-10-09
Public Meeting 1-13-10
Public Meeting 5-19-10
Public Update 1-22-13

Important Links


*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.

 
Updated April 17, 2014

Events

Opening Celebration Photos

Opening Celebration Photos
Saturday, April 12, 2014
You will need adobe acrobat reader to view this document.

Select photo to view event photos.

For More Information

Patrick Donohue
800 Maynard Ave S, Suite 300
Seattle, WA 98134
206-684-9286
patrick.donohue@seattle.gov

Night Out Photo 1st to 2nd Ave
The community celebrated completion of the first block of the park at the National Night Out event on August 6, 2013
— Photo Courtesy of SvR Design

Aerial Photo 1st to 2nd Ave
Aerial Photo 1st to 2nd Ave

— Courtesy of SvR Design

Construction Progress July 2013
Construction July 2013

— Courtesy of SvR Design

Construction March-April 2013
Bell St. Construction March-April 2013


Section View
Section View


Section View
Learn more about the design here


Select any image to open larger version.



 Home | Partnerships | Park Board | Volunteer | FAQ | Parkways Parkways Icon | Facebook Facebook Icon | @SeattleParks Twitter Icon | Flickr Flickr Icon