Timeline

Early 2018

  • Designed phase neighborhood outreach
  • Held community drop-in session
  • Project design continued

Mid 2018

  • Project design continued
  • Permitting and environmental review process

Late 2018

  • Conducted final design phase neighborhood outreach
  • Held community open house

Early 2019

  • Finalize design and award construction contract
  • Pre-construction community notification

Late 2019

  • Construction tentatively scheduled to begin in fall 2019 and take about 12 to 14 months*
  • Construction updates, as needed, via website and listserv

Mid- to Late 2020

  • Complete construction

*Schedule is dependent on weather and other factors.