DPD |
Directors Rule 7-99 |
Applicant:
City of Seattle
|
Page
1 of 6
|
Supersedes:
19-96,
21-96
|
Department of Design, Construction and Land Use
|
Publication:
9/30/99
|
Effective:
10/22/99
|
Subject:
Field Inspection Procedures for Spray-Applied
Fire-Resistive Material (SFRM)
|
Code and Section Reference:
Seattle Building Code Section1701 |
|
Type of Rule:
Code Interpretation
|
|
Ordinance Authority:
3.060.040 SMC |
Index:
Building Code/Technical & Procedural Requirements
|
Approved Date |
PURPOSE
The purpose of this rule is to provide special
inspectors with a standard inspection procedure for spray-applied fire-resistive
material (SFRM) as required by Section 1701.5, Item 10 of the Seattle Building
Code. This rule was developed to provide consistent and accurate inspection
methods.
RULE
1.0 Responsibilities
1.1 Authorization
1.1.1. Inspections of SFRM shall be
made only by a DPD inspector, or a WABO (Washington Association of
Building Officials) or DPD-approved inspection/testing agency, unless
otherwise approved by the building official.
1.1.2. Only special inspectors
registered in the category of SFRM shall perform such inspections
under the supervision of the approved testing/inspection agency.
1.2 Approved
Plans
1.2.1 SFRM SHOP DRAWINGS MUST BE SUBMITTED
TO
AND APPROVED BY DPD PRIOR TO
APPLICATION OF SFRM AS REQUIRED BY DIRECTOR’S RULE 6-99.
All inspections shall be made in
accordance with the DPD-approved shop drawings that clearly identify
the classification (sprayed fiber, or cementitious mixtures) and
density (regular, medium, or high density) of SFRM and the thickness
of SFRM required for the primary, secondary, and other framing
elements.
1.2.2 Members carrying wind and
earthquake forces in combination with gravity loads are included in
the definition of primary structure. Bracing used to reduce the
effective length of a column shall have the same fire resistance
rating as the column.
1.2.3 Structural frame members carrying
only wind or earthquake forces are not required to have a fire
resistance rating.
1.2.4 All reductions in thickness of
the SFRM at beam web penetrations taken according to Section 5.8 below
shall be noted on the DPD-approved shop drawings.
1.2.5 Inspected areas shall be marked on a
reduced plan provided by
the owner and maintained on the
jobsite.
1.3 Preconstruction
Conference
The contractor shall hold a meeting with
the SFRM subcontractor, DPD’s representative, and the special inspector
for the purpose of determining the scope and methods of inspection and
responsibility for "follow-up" inspections, including patching
of damaged and weathered areas. The plans (shop drawings) must be
submitted to DPD, approved, and available at the jobsite prior to this
meeting.
2.0 Request
for Inspection and Scheduling
The person doing the work shall initiate the
request for inspection. It is the responsibility of the general contractor to
ensure that special inspections are scheduled in a timely manner.
3.0 Frequency
of Inspection
Inspections will be required after each floor
or 10,000 square feet to which SFRM has been applied, whichever quantity is
less. Inspections are required for each classification (sprayed fiber or
cementitious mixtures) and density (regular, medium, and high density) of SFRM
applied and for each type of substrate condition encountered (bare, primed,
and painted steel). If substrate conditions change during erection,
inspections will be required of the new conditions. NO SFRM SHALL BE
COVERED PRIOR TO INSPECTION.
4.0 Reports
The approved inspection/testing agency shall
promptly report the results of their inspections in writing to the owner or
the owner’s representative and DPD. Inspections must be recorded on
separate data sheets for each classification and density of SFRM and substrate
condition combination, for example, regular density SFRM over bare steel, or
medium density SFRM over primed steel, etc. One copy of these reports must be
maintained on the jobsite. The report shall be submitted after completion of
SFRM application on each floor or 10,000 square feet, whichever quantity is
less, and at such time as the tested area is still available for ready
correction of cited deficiencies.
5.0 Inspection
Procedure for SFRM
5.1 Prior
Inspections
Verify that all inspections of structural
steel members and connections have been completed in the area to be
sprayed before SFRM application is started.
5.2 Substrate
Condition
The substrate condition shall be inspected
in accordance with UBC Standard 7-6, Section 7.603.2. Substrate
temperature must be at least 40° F at the time of SFRM application and
for at least 24 hours after application. Substrate temperatures down to
35° F may be allowed at the time of application, and for a specified
period after application, if the manufacturer’s published instructions
permit it for the product applied and jobsite conditions. A copy of the
manufacturer’s product application specifications shall be kept on the
jobsite in a readily accessible location until all SFRM inspections and
corrections have been completed.
5.3 Approved
Materials
The SFRM shall be verified as conforming to
the classification and density indicated on the DPD-approved SFRM shop
drawings.
5.4 Preliminary
Thickness Determination for all Structural Frame Members and Floor
Sections
Visually check all structural frame members
and floor sections in each area sprayed. All generalized areas appearing
to be less than required thickness, damaged areas, and dropouts are to be
checked for thickness and marked for recoating where required. The
applicator will be directed to recoat all deficient areas.
5.5 Flutes
and Valleys
Where open flutes or valleys of steel deck
sections occur over beams, they shall be filled solid.
5.6 Special
Considerations for Exposed SFRM Below 8 Feet in Parking Garages When
High-Density SFRM is Specified
When specified, exposed SFRM in parking
garages on those portions of beams, columns, ceilings, or other structural
members less than 8 feet from a floor and in areas subject to vehicular
traffic, must meet the following minimum performance values:
a. a minimum bond strength of 7,000
pounds per square foot (psf) when tested in accordance with ASTM E
736;
b. a minimum compressive strength of
50,000 psf when tested in accordance with ASTM E 761; and
- a minimum density of 35 pcf when tested
in accordance with ASTM E 605.
When applying such SFRM, manufacturer’s
recommended installation procedures shall be followed.
This section does not apply to unexposed
SFRM, such as that protected by a furred wallboard assembly, cement,
cement plaster and lath, or a similar protective construction approved
by the building official.
5.7 Pipe,
Conduit, and Similar Installations
Ducts, conduit, piping, and similar
mechanical, electrical, and plumbing installations shall not be embedded
within the required thickness of the SFRM.
5.8 SFRM
Thickness Reduction at Steel Beam Web Penetrations
SFRM thickness reduction at steel beam web
penetrations, when noted on the shop drawings, must have increased SFRM
thickness on surfaces adjacent to the penetration extending 12 inches in
all directions from the edge of the web penetration. This section only
applies to those SFRM products that have an approved assembly rating that
describes methods for SFRM thickness reductions at flange tips (for
example, 1998 UL Fire Resistance Directory Design Number N782 and N805, as
amended).
5.9 Test
Method for Thickness
The test method for thickness of the SFRM
shall be conducted in accordance with UBC Standard 7-6, Section 7.603.
The random areas selected for test
measurements shall be marked on a reduced floor plan before inspection is
started. Results of test measurements are to be recorded on data sheets.
Test locations on columns and beams are to be selected at the end thirds
or middle thirds, in a rotating order to vary the location of test areas.
It is preferable to conduct thickness tests
before medium and high-density SFRMs have cured and are too hard to test
for thickness using standard procedures. The applicator must adjust the
thickness of the freshly applied SFRM to yield thickness after cure, in
accordance with the SFRM manufacturer’s recommendations. If the tests
are conducted after curing, any holes made to accommodate the
thickness-gauge pin must be closed off immediately following the test
using the same SFRM.
Where thickness is less than that required,
the condition shall be corrected. The location of any uncorrected areas
shall be reported to the building official.
5.10 Test
Methods for Density
The test to determine density of SFRM shall
be conducted in accordance with UBC Standard 7-6, Section 7.604.
Density determinations may be made in
accordance with either Section 7.604.3, or the alternative density
displacement method set forth in Section 7.604.4. DPD equally accepts the
results of either method.
No sample shall have a density less than 5
percent below the specified density. Where the density is less than 5
percent below the specified density, the work shall be corrected to the
satisfaction of the building official.
5.11 Test
Method for Cohesion/Adhesion (Bond-Strength)
The test to determine the cohesion/adhesion
of SFRM shall be conducted in accordance with UBC Standard 7-6, Section
7.605.
At the beginning of SFRM application, at
least one cohesion/adhesion test shall be taken from a column, beam, and
deck at a location representative of the general condition of the
substrate. Additional cohesion/adhesion tests shall be taken whenever the
substrate condition changes, freezing conditions occur within 24 hours
after SFRM application, or the suitability of the substrate is
questionable for any other reason. The tests shall be conducted only after
the in-place SFRM has cured and shall be taken at the location(s) under
question.
At least one cohesion/adhesion test shall
be taken from a column, beam, and deck for exposed SFRM applied as set
forth in Section 5.6 above.
No sample shall have a cohesive/adhesive
force of less than 150 psf. Where the cohesive/adhesive force is less than
150 psf, the work shall be corrected to the satisfaction of the building
official.
5.12 Patching
Inspections
All patching of damaged areas on beams,
columns and bracing at the exterior of the building will be approved by
the inspection agency no more than 24 hours prior to erection of exterior
cladding. All patching of damaged areas on beams, columns, bracing, and
floor sections at the interior of the building must be approved by the
building official before any wall or ceiling cover is allowed.
5.13 Final
Acceptance Inspection
Final inspection will be made when all
corrections are completed. Final inspection of exterior surface shall not
be performed until cladding is completed. SFRM shall not show upon
complete drying or curing any deep or wide cracks, voids, spalls or any
exposure of the substrate. The inspection agency will submit a final
acceptance report and test data sheets to the general contractor and the
building official on completion of each floor.
|