Timeline

Timeline

2018

  • Q1 (January-March): Confirm replacement pipe alignment, public outreach
  • Q2 (April-June): Complete 30% design and apply for external permits
  • Q3 (July-September): Advance design to 60% completion
  • Q4 (October-December): Finalize design, receive external permits and approvals, acquire contractor

2019

  • Q1 (January): Contractor mobilizes to project sites, construction begins