Timeline

  • 2017 — 2018
    Site master plan development
  • 2017 — 2020
    Pump station design
  • 2017 — 2020
    Ballard conveyance design
  • 2018 — 2019
    Site preparation and pier construction
  • 2019 — 2023
    Tunnel construction
  • 2022 — 2024
    Conveyance pipes
  • 2022 — 2025
    Pump station construction
  • 2024 — 2025
    Restore 24th Avenue NW street end
  • 2024
    Pier open for public use