Seattle Public Utilities Mami Hara, General Manager/CEO

Venema Creek

Natural drainage system

Natural drainage system cells and plantings in the Broadview neighborhood.

Timeline

  • November 2014
    Construction began
  • December 2015
    One of the wettest months ever in Seattle – Heavy rains slowed down planting efforts
  • January 2016
    Project substantially complete

Connect


Andrew Ng, PMP
andrew.ng@seattle.gov
(206) 386-4027