Thornton Creek Confluence

Project Schedule:

  • July 2012: 60% project design released
  • August 2 and 4, 2012: 60% design public meeting and drop-in question/answer session
  • August 31, 2012: Deadline for public comments on 60% design
  • November 14th, 2012 design update meeting
  • September 2013: SEPA Checklist released for public review and comment
  • Fall 2013 - Winter 2014: Project design completed, community briefings
  • February 2014: Project out for construction bid
  • April - May 2014: Project pre-construction work starts, including tree removal, utility relocation
  • May 2014: Construction anticipated to begin
  • October 2014: Anticipated project completion