The South Lake Union Streetcar: Construction Guide May 2007The Seattle Streetcar Monthly Construction Guide previews upcoming construction activities for the South Lake Union Streetcar Project. The construction guide provides general information about the type and duration of work and traffic control plans. During construction the Project team will make every effort to minimize construction impacts to local businesses and residents. Please note, some changes and adjustments to the schedule and scope of work are likely. For more information please contact Josh Stepherson, Streetcar Community Liaison, at (206) 684-3136. In May 2007, the Seattle Streetcar Team will substantially complete advanced storm work related to the project. The Streetcar contractor, Stacy & Witbeck, will begin to install track in the downtown area. Work setting trolley pole foundations, the Streetcar maintenance facility and pavement restoration on Westlake and Fairview will continue. DOWNTOWN AREA Westlake Avenue between Olive Way and Denny Way ADVANCED UTILITY WORK √ Achieved substantial completion for advanced utility work related to the Seattle Streetcar Project. ELECTRICAL Foundation installation for street lighting, traffic signals, signal interconnect work and platform electrical services being installed.
OVERHEAD CATENARY SYSTEM Construct pole foundations on Westlake between Olive Way and Denny Street . Saw cut, excavate 3x3 hole approximately 18’ feet deep, set rebar, anchor plate and foundation for pole mounting. *Note: Poles will be set a future date.
TRACK INSTALLATION Install Streetcar track thru the intersection of Westlake Avenue and Denny Street
Traffic control: Intersection of Denny and Westlake closed to east/west traffic during construction hours. Install Streetcar track on west side of Westlake Avenue between Denny Street and Virginia Street
Traffic control: One lane in each direction maintained. Parking on both sides of Westlake Avenue restricted near construction zone. SOUTH LAKE UNION AREA ADVANCED UTILITY WORK √ Achieved substantial completion for advanced utility work related to the Seattle Streetcar Project. TRACK INSTALLATION Complete track installation on Westlake Avenue between Denny Street and Valley.
Complete installation of two more Streetcar platforms. Westlake/Mercer platform
Westlake platform between Thomas & Harrison
Install Streetcar track switch on Fairview Avenue North near Yale Street
Note: In many locations along Westlake Avenue there is a difference between the track and existing street level. In late May, the contractor will grind and overlay the street with asphalt to address this issue. Between now and the grind & overlay the contractor will put cold mix down in areas where they are not working to allow for more parking along Westlake Avenue. STREET IMPROVEMENTS Curb and drive-way replacement along Fairview Avenue North
Repave the northeastern portion of the Westlake and Thomas sidewalk
OVERHEAD CATENARY SYSTEM Construct joint-use pole foundations Saw cut, excavate 3x3 hole approximately 18’ feet deep, set rebar, anchor plate and foundation for pole mounting. *Note: Poles will be set a future date.
MAINTENANCE FACILITY Constructing the foundations, excavating maintenance pit, erecting concrete walls.
Previous Month Constructions Reports: |
|