![]()
|
The South Lake Union Streetcar: Construction Guide March 2007The Seattle Streetcar Monthly Construction Guide previews upcoming construction activities for the South Lake Union Streetcar Project. The construction guide provides general information about the type and duration of work and traffic control plans. During construction the Project team will make every effort to minimize construction impacts to local businesses and residents. Please note, some changes and adjustments to the schedule and scope of work are likely. For more information please contact Josh Stepherson, Streetcar Community Liaison, at (206) 684-3136. In March 2007, the Seattle Streetcar Team will perform work related to installing track drain leads in the downtown area, continue to set traffic signal and catenary pole foundations, start foundation construction at the Streetcar maintenance facility and start pavement restoration along Fairview . The contractor expects to achieve substantial completion of Streetcar trackway on Terry Avenue and Harrison Street . In addition, work related to Seattle Public Utilities (SPU) water facilities will conclude at the end of the month. The Streetcar contractor is performing additional electrical utility improvement work on behalf of Seattle City Light at two locations in South Lake Union. Seattle City Light crews are also making electrical system improvements in the area. DOWNTOWN AREA ADVANCED UTILITY WORK OVERHEAD CATENARY SYSTEM Construct joint-use pole foundations on Westlake between Olive Way and Denny Street. Saw cut, excavate 3x3 hole approximately 18’ feet deep, set rebar, anchor plate and foundation for pole mounting. *Note: Poles will be set a future date.
Install signal interconnect system for Westlake between Olive Way and 9th Saw cut, excavation, duct bank and vault installation, backfill and temporary restorations.
SOUTH LAKE UNION AREA ADVANCED UTILITY WORK Complete the decommissioning of waterline at Denny Way and Westlake Avenue.
Complete installation of SCL vault and duct bank on eastern sidewalk of Westlake Avenue just south of Thomas Street. Excavate, set 8’x14’ vault, set conduit and backfill.
Install Streetcar track drain leads at SW corner of Republican Street and Westlake Avenue. Excavate, shore, install track drains and back fill. This work requires deep excavation(10 – 20 feet deep).
Install storm track drain, 8” tie-in and 4” inlet on Westlake Avenue between Thomas Street and Harrison Street.
Install a SCL duct bank on the west side of the intersection of Fairview Avenue and Harrison Street. Saw cut, excavate 4 to 8 feet deep, set conduit and backfill.
TRACK INSTALLATION Excavate, construct rail, and pour track slab. This work features a shallow trackway excavation and installation of rail. Construction will typically occur during normal business hours and will not require road closures. Complete installation of Fairview Avenue Streetcar platform. Between Aloha Street and Yale Street
*Track installation on Fairview Avenue between Valley Street and Yale Street is substantially complete. Complete installation of streetcar rail on Terry Avenue between Thomas Street and Republican Street.
Complete streetcar rail installation on Harrison Street between Terry Avenue and Fairview Avenue.
Streetcar rail installation at the Harrison Street and Fairview Avenue intersection.
(Week of 3/19) Fairview Avenue restricted to one lane in each direction. Harrison Street closed to thru traffic. (Week of 3/25) During non-peak hours traffic will be channeled to one north and south bound lane near the Fairview/Harrison intersection. Two south bound lanes will be maintained during the morning rush-hour commute (7:00 a.m. to 9:00 a.m.) Two north bound lanes will be maintained during the afternoon rush-hour commute (4:00 p.m. to 6:00 p.m.).Eastbound on Harrison Street off of Fairview Avenue North will be closed. One lane westbound on Harrison Street will be maintained. Streetcar rail installation on Westlake between Mercer Street and Republican Street
Construct the Westlake/Mercer Streetcar platform.
Streetcar rail installation on Westlake between Republican Street and Harrison Street.
FAIRVIEW AVENUE ROADWORK In front of the Marriott Inn’s eastern driveway repave a 40’ segment of the southern most lane on Fairview Avenue North and the adjacent sidewalk.
Repave the northern portion of the Valley and Fairview intersection
OVERHEAD CATENARY SYSTEM Construct joint-use pole foundations on Westlake between Denny Street and Mercer Street. Saw cut, excavate 3x3 hole approximately 18’ feet deep, set rebar, anchor plate and foundation for pole mounting. *Note: Poles will be set a future date.
MAINTENANCE FACILITY Set the foundations, footing and first floor walls for the streetcar maintenance facility.
Previous Month Constructions Reports: |
|