The South Lake Union Streetcar: Construction Guide July 2007The Seattle Streetcar Monthly Construction Guide previews upcoming construction activities for the South Lake Union Streetcar Project. The construction guide provides general information about the type and duration of work and traffic control plans. During construction the Project team will make every effort to minimize construction impacts to local businesses and residents. Please note, some changes and adjustments to the schedule and scope of work are likely. For more information please contact Josh Stepherson, Streetcar Community Liaison, at (206) 684-3136. In July 2007, the Seattle Streetcar Team will complete installation of track in the downtown area, install sub-stations, continue to set trolley poles, conclude the grind & overlay of Westlake Avenue and re-stripe roadway. Work will continue on the Streetcar maintenance facility. DOWNTOWN AREA Westlake Avenue between Olive Way and Denny Way Achieved substantial completion for advanced utility work related to the Seattle Streetcar Project. √ Completed installation of streetcar trolley pole foundations √ Installed Streetcar track between 9 th Avenue and Virginia Street TRACK INSTALLATION Install Streetcar track on Westlake Avenue between Stewart Street and Virginia Street
ELECTRICAL Continue work related to street lighting, traffic signals, signal interconnect work and platform electrical services. STREET IMPROVEMENTS Start work related to grinding and Repaving Westlake Avenue between Olive Way and Denny Street . Start date last week of July to be determined. SOUTH LAKE UNION AREA √ Achieved substantial completion for advanced utility work related to the Seattle Streetcar Project. √ Achieved substantial completion for track installation on Westlake Avenue and Terry Avenue between Denny and Mercer. TRACK INSTALLATION Start Track installation in Valley Street railbank Duration: June 28 th – mid-August Complete installation of Westlake/Mercer platform. Westlake/Mercer platform
Install Streetcar track switch on Fairview Avenue North near Yale Street
Complete Grind & Overlay on Westlake Avenue between Harrison Street and Mercer Street
STREET IMPROVEMENTS SW Curb at Mercer Street and Westlake Avenue
SW Curb at Harrison Street and Westlake Avenue
MAINTENANCE FACILITY √ Constructed the foundations, excavated maintenance pit, erected concrete walls.