Working for a safe, affordable, vibrant, innovative, and interconnected city.
Learn More
Seattle.gov Home Page
Seattle.gov This Department
Link to Transportation Home Page Link to Transportation Home Page Link to Transportation About Us Page Link to Transportation Contact Us Page
Delivering a first-rate transportation system for Seattle Scott Kubly, Director

Services 

Projects 

Planning 

Resources 

Events

News

Site Index


Street Maintenance Program
Pavement Management
Current Paving Projects
Recent Paving Projects
Bridge Projects
Bridge Painting Projects
Bridge Rehabilitation, Replacement and Seismic Retrofit
Pothole Rangers
Street Maintenance Request Form

2010 Asphalt Arterial & Concrete Spot Rehabilitation - Nickerson Street

Project Update – October 21, 2010

Substantially complete October 7th, however most work completed earlier.  Project had 55 Work Days in contract - 50 Working Days expended.


Project Update – September 29, 2010

Construction work along Nickerson is substantially complete.


Construction Update:  August 11, 2010

Nickerson Street to be Reduced to One Lane for Repaving Work This Week

On Wednesday and Thursday August 11th and 12th Nickerson Street will be repaved between 4th Avenue N and Etruria Street.  Work will begin at 7:00 p.m. Wednesday evening and continue until 5:30 a.m. Thursday morning.  

Nickerson will be reduced to one lane during the paving.  Two-way traffic will alternate use of the lane.

Uniformed Police Officers (UPOs) will be on-site to coordinate traffic. There will be short-term traffic restrictions on cross streets and pedestrian detours.

 

PROJECT UPDATE – July 26, 2010

Construction to Start Week of July 26th

As part of its 2010 Arterial, Asphalt, and Concrete (AAC) program the City of Seattle Department of Transportation (SDOT), and its contractor Gary Merlino Construction, will be repaving a section of Nickerson Street in the lower Queen Anne neighborhood this summer. We will also be rechannelizing Nickerson Street to improve pedestrian and bicycle safety while accommodating traffic flows on this key arterial.

This project is primarily a pavement maintenance and traffic lane reconfiguration effort.

Tentative Construction Schedule

Construction work is scheduled to begin July 26th and continue into late August. Normal working hours will be between 7:00 a.m. to 4:00 p.m. Grinding off the top layer of asphalt and repaving of the roadway is expected to occur at night and is scheduled to take a total of 3 days during the first and second weeks in August.

The tentative sequence of work is as follows:

  • Last week of July – Mobilization and layout for rechannelization
  • First week of August – New concrete panels at Etruria Street and new curb ramps in various locations
  • Two days during the first week of August – Asphalt grinding (pavement removal)
  • First and second weeks of August -- Roadway base repairs and utility adjustments
  • One day later in the week of August 9 thru 13 – Asphalt pavement overlay
  • First three to four weeks of August – Remove and replace channelization/pavement striping
  • Last part of August – Finalize work and clean up

Project Contacts:

Bob Derry, Construction Communications Officer, bob@stephersonassociates.com (206) 250-2865
George Frost, Public Outreach Coordinator, george.frost@seattle.gov (206) 615-0786
Susan Byers, Project Manager, susan.byers@seattle.gov, (206) 733-9076

For more information on the rechannelization project see: http://www.seattle.gov/transportation/nickerson.htm

Project Overview

Bridging The Gap LogoAs part of its 2010 Arterial Asphalt and Concrete (AAC) Program, the Seattle Department of Transportation (SDOT) is planning to repave a section of Nickerson Street in the lower Queen Anne neighborhood.

This paving project is funded by the “Bridging the Gap” transportation levy approved by Seattle voters in November 2006. 

Project Location:

Nickerson Street, from13th Avenue W (near Ballard Bridge) to Fourth Avenue N (Fremont Bridge). 

Project Description:

This project is primarily a pavement maintenance and traffic lane reconfiguration effort.  The two main components of the project are:

  • Resurfacing the asphalt pavement on Nickerson Street between Etruria Street and 4th Avenue N to make the surface smoother and safer for traffic
  • Rechannelizing W Nickerson Street between 13th Avenue W and Etruria Street to reduce the number of traffic lanes to one in each direction and add bike lanes on the uphill (westbound) direction.  Sharrows’ (arrows that are painted on the roadway to indicate bicycle use) will be added to the downhill (eastbound) direction.  

The project will also have some curb ramps rebuilt for better pedestrian access.

Project Schedule:

Construction work is scheduled to begin in mid-July and continue through September.  More detailed schedule information will be provided prior to the start of construction.

For additional Nickerson Street rechannelization information, click here

What to Expect During Work:

  • Lane closures
  • Pedestrian detours
  • Parking and loading restrictions
  • Construction noise and dust
  • Instances of weekday, weekend and night work
  • Regular notices with more location specific information during construction
  • Some of this work is weather dependant, and the schedule may be adjusted as the project moves forward

Project Contacts:

George Frost, Public Outreach Coordinator, george.frost@seattle.gov (206) 615-0786
Susan Byers, Project Manager, susan.byers@seattle.gov , (206) 733-9076


Subscribe to E-Mail Alerts

SDOT Paving Projects List

E-mail:  

Subscribe (Join the list)

Unsubscribe (Remove me from the list)

  
Home | About Us | Contact Us | Site Index | News | FAQs | E-Mail Alerts