Seattle.gov Home Page
Seattle.gov This Department
Link to Transportation Home Page Link to Transportation Home Page Link to Transportation About Us Page Link to Transportation Contact Us Page
A vibrant Seattle through transportation excellence Peter Hahn, Director

Services 

Projects 

Planning 

Resources 

Events

News

Site Index


Seawall Home
Environmental Impact Statement
Project Library
Concept Plans & Drawings
Project Calendar
Stakeholder Subgroup
Seawall Habitat
Glossary
Peer Cities
Photo Archive
Background Information
Contact
U.S. Army Corps of Engineers
Waterfront Seattle
Alaskan Way Viaduct

Additional background information

The Seawall Today

The Significance of the Seawall

What's at Risk?

Frequently Asked Questions

Seawall Scientific Habitat Enhancement Study

Timeline

DATE EVENT

December 5, 2012

Draft Environmental Impact Statement Open House

November 13 – December 13, 2012

Draft Environmental Impact Statement Public comment period

November 2012

Mortenson/Manson selected as the General Contractor/Construction Manager for construction

November 2012

Proposition 1 approved by Seattle voters to complete funding needed for Phase 1/Central Seawall construction

Fall 2012 Light Penetrating Surfaces Study installed at Pier 62/63
July 2012 Seattle City Council placed $290 million bond measure on the November 6, 2012 ballot; Mayor McGinn signed the legislation on July 17, 2012

May 2012

Field work and surveying on the waterfront

April 2012 Alternative C and updated 35% design costs
April 2011

Seawall Alternatives A & B, updated cost estimates announced

January 2011 Seawall Stakeholder Subgroup becomes larger: city of Seattle convenes first Central waterfront Stakeholder Group meeting for both Elliott Bay Seawall Project and Waterfront Seattle
January 19 – February 8, 2011 Public comment period (including public open house)
July 2010 – November 2010 Project planning and conceptual design process in coordination with Seawall Stakeholder Subgroup
July 2010 City of Seattle convenes Seawall Stakeholders Subgroup to provide input on seawall alternatives development and construction.
June 16, 2010 Scoping Meeting
June 1 – July 19, 2010 Public comment on scoping
Spring 2010 The City of Seattle selects the Tetra Tech consultant team to carry out the work to replace the Seawall.
Fall 2009 The City of Seattle releases a Statement of Qualifications seeking consultants with experience in innovative seawall design and construction, engineering, environmental analysis and documentation, economic analysis, and public involvement.
2002 - 2007 Ekki wood facing removed, sheet pile wall patched, and a new cathodic protection system was installed at Clay Street.
2001 Approximately 300 lineal feet of street adjacent to Waterfront Park settled due to a combination of liquefaction from the Nisqually earthquake and voids caused by deterioration of the Type A timber relieving platform.
1999 Repairs made to Ekki wood facing. Pea gravel behind facing was eroded in some areas potentially exposing retained fill to further erosion.
1987 Repairs on Type B seawall timber platform at Clay Street included adding Ekki wood facing to all Type B steel sheet piles to help retain bulkhead-supported soils where sheet piles were corroding.
1956 - 1961 Cathodic protection installed on Type B wall at Clay street. Despite the cathodic protection measures, new holes continue to appear in sheet piling.
1951 – 1955 Corrosion first noted in the steel sheet pile wall. Patch repairs were made in 1951. The later discovery of leaks and a large void under both the relieving platform and Alaskan Way led to the excavation and backfilling in August 1954. Further sheet pile patching and grouting below the platform occurred in 1954 & 1955. The seawall supported roadway near Clay Street sank 2 feet during this time.
1947 First holes appear in Type B sheet pile wall due to corrosion. Fill begins to be washed out from behind the wall.


Home | About Us | Contact Us | Site Index | Events | News | FAQs | E-Mail Alerts