|
Pavement Type: New pavement shall be of the same type (rigid or flexible) as the existing pavement when a street is being widened, extended, or replaced unless otherwise directed by Seattle Department of Transportation.
Pavement Depth: Pavement depth is determined by a pavement design and is based on the zoning, number and type of heavy vehicles per day using or expected to use the roadway, the strength of subgrade, and the type of pavement being designed. Required pavement sections are provided in the Pavement Opening and Restoration Rules (PORR). The pavement sections provided in the PORR were developed to accommodate the varying design conditions (soil types, drainage conditions, etc) found throughout the City of Seattle and are fairly conservative.
If a project proposes to use a pavement section less than the one specified in the PORR, then a pavement design must be approved by SDOT. The design should be based on specific site criteria and the design parameters described below. For designed pavements, subgrade testing and analysis by a geotechnical engineer, a traffic analysis, and pavement design calculations are required. Subgrade strength tests (CBR, k-value, R-value, etc.) shall be performed by a qualified geotechnical engineer.
Alley Pavement Depth:
|
Land Use Zone
|
Pavement Type and Depth
|
|
1 or 2 new dwelling units
|
6" crushed rock
|
|
SF, LR1, LR2, LR3, MR, HR |
6" Portland cement concrete or 3" asphalt concrete over 6" crushed rock
|
|
NC1, NC2, NC3
|
8" Portland cement concrete or 3" asphalt over 7" crushed rock
|
|
C1, C2, IB, IC, IG1, IG2 and Downtown
|
8" Portland cement concrete
|
Pavement Design: Default Design Parameters for New Pavement
|
Initial Serviceability Index (P i)
|
4.5
|
|
Terminal Serviceability Index (P t)
|
2.0
|
|
Reliability
|
90%
|
|
Asphalt Design Life
|
20 years
|
|
Asphalt Standard Deviation
|
0.45
|
|
Structural Coefficient Asphalt HMA Class ½” and Class 1”
|
0.39
|
|
Structural Coefficient Mineral Aggregate Type 2, Crushed Rock
|
0.13
|
|
Concrete Design Life
|
40 years
|
|
Concrete Standard Deviation
|
0.35
|
|
Joint Load Transfer Coefficient
|
3.2
|
|
Modulus of Concrete Rupture
|
650 psi
|
|
Modulus of Concrete Elasticity
|
4.0 x 106 psi
|
|
Drainage Coefficient
|
1.0
|
The inputs in the table above should be used as a starting point for pavement design and adjusted as needed to reflect the specific project conditions. Pavement design reports should describe how each input value was developed. Pavement design on roadways that accommodate a high volume of heavy vehicles, including Major Trucks Streets, streets included in the Transit Classifications, Regional Connectors, Commercial Connectors, and Industrial Access streets shall be designed using the 1993 AASHTO Guide for the Design of Pavement Structures, 4th Edition with 1998 Supplement.
Panel Layout: When new PCC pavement is proposed or required, the panel layout at all intersections and on arterial streets must be shown on the plans. Additionally, panel layouts may be required for non-arterial streets with non-standard street widths. Longitudinal joints must be placed so that they are not within the wheel path of vehicles or in an area used by bicycles. The joints, dowel bars, and tie bars shall be per Standard Plan 405a through 405d.
Pavement subgrade: The pavement shall be placed on a prepared subgrade of properly compacted suitable material as determined by Seattle Department of Transportation (SDOT).
Compaction of subgrade: The subgrade must be compacted to at least 95% of maximum dry density for all street and alley improvements. Subgrade materials that cannot be compacted to this density shall be over-excavated (removed) and the subgrade replaced with acceptable material.
Soil tests: Soil density tests may be required during construction to show that the required degree of compaction has been obtained.
Limits of pavement replacement and restoration: The extent of new pavement to be installed on roadways with existing pavement depends on required pavement width and existing pavement conditions. Specific rules and requirements for new pavement are detailed in the Street and Sidewalk Pavement Opening and Restoration Rules.
Existing and proposed concrete panel joints shall be shown on street improvement plans for all intersections, arterial streets and when the pavement restoration will exceed one block. The extent of pavement replacement shall be depicted on street improvement plans by shading panels, or portions of panels, to be replaced. |