District 7 - Project Updates
2017 Your Voice, Your Choice: Parks and Street Elected Project

STREETS | Queen Anne Area Upgrades

Crossing Upgrades

Project Description and Goals:
Multiple crossing locations along Queen Anne Ave N experience high pedestrian and vehicle volumes. Marking crosswalks improves visibility, and installing curb bulbs shorten crossing distances, make pedestrians more visible and calms traffic.

Project Solution(s):

Install a curb bulb on the northeast corner of 3rd Ave W and W Galer St 

Mark crosswalk at 6th Ave W and W Crockett St, north crossing

Mark crosswalk at Queen Anne Ave N and W Howe St, north crossing

Construction was completed in July 2018.

Queen Anne crossing upgrades map

Back to top.
Back to Your Voice, Your Choice landing page.

STREETS | 4th Ave N, Raye St and Queen Anne Dr

Crossing Upgrades

Project Description and Goals:
On the north end of Queen Anne Dr, a large, 7-way intersection presents a tricky situation for all travelers making their way to or under, the SR-99 Aurora Bridge. Large swathes of pavement combined with a lack of crosswalks and ADA ramps makes this a unique and challenging space. We're modifying it to enhance safety and improve predictability.

Project Solution(s):

Install a raised crosswalk

Install a curb bulb

Add ADA accessible curb ramps

Trim landscaping

Construction anticipated in early 2020.

4th Ave north, Raye street and Queen Anne Drive crossing upgrades map

Back to top.
Back to Your Voice, Your Choice landing page.

STREETS | 1st Ave N and Thomas St

Crossing Upgrades

Project Description and Goals:
The intersection of 1st Ave N and Thomas St experiences extremely high pedestrian demand and vehicle traffic due to its proximity to the Seattle Center. The intersection lacks a signal and marked crosswalk to assist pedestrian crossings. Adding a marked crosswalk and crossing beacons enhances safety for people walking, biking and driving.

Project Solution(s):

Install a marked crosswalk on the north side of 1st Ave N and Thomas St

Install a pair of crossing beacons

This project has been cancelled in lieu of the Seattle Center Arena Project Community Benefits package. Please check the Seattle Center Arena project website for the latest updates.

1st ave and Thomas street crossing upgrades map

Back to top.
Back to Your Voice, Your Choice landing page.

Materials