DISTRICT 7 - PROJECT UPDATES
2017 Your Voice, Your Choice: Parks and Street Elected Project

Queen Anne Area Upgrades

Crossing Upgrades

Project Description and Goals:
Multiple crossing locations along Queen Anne Ave N experience high pedestrian and vehicle volumes. Marking crosswalks improves visibility, and installing curb bulbs shorten crossing distances, make pedestrians more visible and calms traffic.

Project Solution(s):

Install a curb bulb on the northeast corner of 3rd Ave W and W Galer St 

Mark crosswalk at 6th Ave W and W Crockett St, north crossing

Mark crosswalk at Queen Anne Ave N and W Howe St, north crossing

Construction completed July 2018

Queen Anne crossing upgrades map

Back to top

Back to program landing page

4th Ave N, Raye St and Queen Anne Dr

Crossing Upgrades

Project Description and Goals:
On the north end of Queen Anne Dr, a large, 7-way intersection presents a tricky situation for all travelers making their way to or under, the SR-99 Aurora Bridge. Large swathes of pavement combined with a lack of crosswalks and ADA ramps makes this a unique and challenging space. We're modifying it to enhance safety and improve predictability.

Project Solution(s):

Install a raised crosswalk

Install a curb bulb

Add ADA accessible curb ramps

Trim landscaping

Construction anticipated October - December 2018

4th Ave north, Raye street and Queen Anne Drive crossing upgrades map

Back to top

Back to program landing page

1st Ave N and Thomas St

Crossing Upgrades

Project Description and Goals:
The intersection of 1st Ave N and Thomas St experiences extremely high pedestrian demand and vehicle traffic due to its proximity to the Seattle Center. The intersection lacks a signal and marked crosswalk to assist pedestrian crossings. Adding a marked crosswalk and crossing beacons enhances safety for people walking, biking and driving.

Project Solution(s):

Install a marked crosswalk on the north side of 1st Ave N and Thomas St

Install a pair of crossing beacons

Construction anticipated 2019

1st ave and Thomas street crossing upgrades map

Back to top

Back to program landing page